BLD-Final | 6/1/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Mike Jordan
|
|
|
Phil Phone #: ###-####
|
DOC - Permit Finaled | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Mike Jordan
|
|
|
All work has been completed.
|
BLD-Framing/Rough-in | 5/25/2017 | 5/26/2017 | 5/26/2017 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Framing on 3 hr wall..... Usful Glassworks side OK.
|
BLD-Final | 4/17/2017 | 4/17/2017 | 4/17/2017 | P | PART |
Mike Jordan
|
|
|
Phil Phone #: ###-####. All intumescent paint is completed for 2hr. fire walls and mill thicknesses verified by MTI. 3hr. fire wall completed on nerfed side, Need to complete on useful glassworks side.
|
FIRE-Final Inspection | 4/14/2017 | 4/17/2017 | 4/17/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Mike Jordan
|
|
|
3hr. firewall on nerf side completed.
|
BLD-Framing/Rough-in | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PART |
Mike Jordan
|
|
|
work in progress on 3rd layer.
|
BLD-Framing/Rough-in | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | PART |
Mike Jordan
|
|
|
Phil Phone #: ###-####. Work in progres on installing the 2nd. and 3rd layers of sheet rock for 3hr. fire wall.
|
Extend Permit 90/180 days | 4/3/2017 | 4/3/2017 | 4/3/2017 | A | PART |
Mike Jordan
|
|
|
Phil Phone #: ###-####. Work in progress on sheet rock at 3hr. wall. !st. layer and partial 2nd.layer. and partial 3rd. layer at wall infill.
|
BLD-Conference | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | DONE |
Mike Jordan
|
|
|
Phil Phone #: ###-####
|
FIRE-Final Inspection | 3/28/2017 | 3/29/2017 | 3/29/2017 | A | FAIL |
Troy Cobbley
|
|
|
I performed a courtesy inspection since no IFC review comments had been provided. The corrections I found apply to all three BLD permits which include BLD16-01070, BLD16-02734 and BLD16-02747. BLD16-02747 was actually still in review status due to a plan modification. Corrections I noted are, new double doors not installed, existing door infilled in Corridor 12, opening infilled in Birthday Room, doors not shown, hardware not allowing direction of egress travel, non-compliant ADA hardware in egress path, door in egress path non-functional, egress path corridor blocked with storage, permanant walls installed that are not shown on the plans that also block view of exit signs, cloth mesh blocking view of exit signs, issues of foam, rubber tire storage, plastic inflatables and plastic barrels (quantity and storage arrangement) in the NERF tenant and the issues of large amounts of foam (mats) in the Gymnastic tenant., also one fire extinguisher was missing and another was mounted too high.
|
BLD-Framing/Rough-in | 3/20/2017 | 3/21/2017 | 3/21/2017 | A | PASS |
Mike Jordan
|
|
|
Please call ahead for access - Phil Phone #: ###-####
|
BLD-Conference | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | DONE |
Mike Jordan
|
|
|
Phil Phone #: ###-####. Went over approved plans and framing details.
|
BLD-Conference | 2/21/2017 | 2/28/2017 | 2/28/2017 | P | PEND |
Mike Jordan
|
|
|
Phil Phone #: ###-####. Need the city approved set of plans before proceeding.
|