BLD-Conference | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | DONE |
Tell Riley
|
|
|
owner stated project is in litigation with previous contractor//let supervisor know what is going on//
|
BLD-Conference | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | DONE |
Tell Riley
|
|
|
Status? Any change?//left notice permit will expire in 10 days, follow up has been scheduled//also other construction demo located in driveway, left notice to obtain permit if needed//
|
BLD-Conference | 10/16/2019 | 10/21/2019 | 10/21/2019 | A | DONE |
Tell Riley
|
|
|
Status?//no one home//plumbing is expired//electrical and mechanical have been finaled//
|
BLD-Conference | 2/21/2019 | 2/22/2019 | 2/22/2019 | P | DONE |
Jim Sly
|
|
|
Check status if not completed give notice that permit will be expired. Work in progress..........
|
BLD-Conference | 11/20/2018 | 11/27/2018 | 11/27/2018 | P | DEFR |
Mike Jordan
|
|
|
Check status if not completed give notice that permit will be expired.
|
BLD-Conference | 3/6/2018 | 3/8/2018 | 3/8/2018 | P | DONE |
Jim Sly
|
|
|
Status? Same..........
|
BLD-Conference | 1/10/2018 | 1/11/2018 | 1/11/2018 | A | DONE |
Jim Sly
|
|
|
Status? Slow progress.....homeowners in charge of completing project.....Work in progress.
|
BLD-Conference | 10/31/2017 | 11/1/2017 | 11/1/2017 | P | DONE |
Jim Sly
|
|
|
Status ? Home owners completing project......Work in Progress.
|
BLD-Aging Inspection | 8/24/2017 | 8/24/2017 | 8/28/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 8/23/2017 | 8/23/2017 | 8/28/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Other | 7/25/2017 | 7/25/2017 | 7/25/2017 | A | PEND |
Jim Sly
|
|
|
Project status? Original Contractor no longer working on project. Home owners are finishing up. Slow......but Work in Progress.
|
BLD-Other | 7/17/2017 | 7/24/2017 | 7/25/2017 | P | DEFR |
Dave Hannah
|
|
|
Project status?
|
BLD-Conference | 4/11/2017 | 4/12/2017 | 4/11/2017 | A | CANC |
Jim Sly
|
|
|
Juile ###-#### Tony Phone #: ###-#### Talked with Julie.....We cancelled.
|
BLD-Framing/Rough-in | 4/10/2017 | 4/12/2017 | 4/11/2017 | A | PART |
Jim Sly
|
|
|
Tony-stairways Phone #: ###-#### Interior stairway OK......excluding Handrails.
|
BLD-Framing/Rough-in | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | NR |
Jim Sly
|
|
|
Tony Phone #: ###-####
|
BLD-Other | 3/2/2017 | 3/3/2017 | 3/3/2017 | P | DONE |
Jim Sly
|
|
|
Check status of project. Work in Progress.
|
BLD-Other | 11/7/2016 | 11/7/2016 | 11/8/2016 | P | PASS |
Jim Sly
|
|
|
Scott// exterior stairs Phone #: ###-#### Exterior stairs....OK
|
BLD-Framing/Rough-in | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | FAIL |
Jim Sly
|
|
|
Stairs // Chris Phone #: ###-#### Called for stair inspection. Contractor has been remodeling and adding to stairs to meet Minimum code for rise and run......C/N posted for headroom clearance per R-311.7.2 2012 IRC.
|
BLD-Framing/Rough-in | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | NR |
Jim Sly
|
|
|
Stairway // Chris Phone #: ###-####
|
BLD-Foundation | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | PART |
Jim Sly
|
|
|
Scott-wall-egress stairs Phone #: ###-#### South and West walls .....OK at exterior stairway.
|
BLD-Foundation | 10/25/2016 | 10/25/2016 | 10/25/2016 | P | PART |
Jim Sly
|
|
|
Cody Phone #: ###-#### East stairway wall...OK.
|
BLD-Footing | 10/20/2016 | 10/20/2016 | 10/25/2016 | P | PASS |
Jim Sly
|
|
|
Jarid Phone #: ###-####
|
BLD-Framing/Rough-in | 10/18/2016 | 10/18/2016 | 10/18/2016 | P | NR |
Jim Sly
|
|
|
Chris Phone #: ###-#### Previously I passed the framing inspection, but that did not include the stairway. The contractor wanted to insulate and cover the new walls. I told him, since they were still working on stairway, I would check at final. called for stair inspection but not ready.
|
BLD-Conference | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | DONE |
Jim Sly
|
|
|
John Phone #: ###-####
|
BLD-Conference | 9/6/2016 | 9/8/2016 | 9/8/2016 | A | CANC |
Jim Sly
|
|
|
July Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PART |
Jim Sly
|
|
|
Chris Phone #: ###-#### Structural steel beams in bsmnt....OK.
|
BLD-Energy code compliance | 7/25/2016 | 7/25/2016 | 7/25/2016 | P | PASS |
Jim Sly
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Jim Sly
|
|
|
Chris Phone #: ###-####
|
BLD-Other | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | PASS |
Jim Sly
|
|
|
steam wall // Chris Phone #: ###-####
|
BLD-Foundation | 5/24/2016 | 5/25/2016 | 5/25/2016 | A | PART |
Jim Sly
|
|
|
Basement foundation - Cody Phone #: ###-#### Footings ok.
|
BLD-Conference | 10/5/2016 | 10/6/2016 | | A | |
Jim Sly
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 10/5/2016 | 10/5/2016 | | P | |
Jim Sly
|
|
|
Chris Phone #: ###-####
|