BLD-Final | 6/3/2016 | 6/6/2016 | 6/15/2016 | A | PASS |
Dave Hannah
|
|
|
Luke Phone #: ###-####
|
DOC - Permit Finaled | 6/15/2016 | 6/15/2016 | 6/15/2016 | A | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 6/14/2016 | 6/14/2016 | 6/14/2016 | P | PASS |
Jim Page
|
|
|
Fire alarm panel shows system is normal, final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 6/9/2016 | 6/10/2016 | 6/10/2016 | P | PART |
Jim Page
|
|
|
Life fire safety inspection passed/complete for level 4, this is the last floor for inspection with this permit. Fire panel was still showing troubles with the alarm system at time of inspection, life fire safety inspection for this permit cannot be finaled until fire panel reads system is normal.
|
FIRE-Final Inspection | 5/24/2016 | 5/25/2016 | 5/25/2016 | A | PART |
Jim Page
|
|
|
Life fire safety inspection complete for level 3
|
BLD-Energy code compliance | 5/12/2016 | 5/16/2016 | 5/16/2016 | A | PART |
Dave Hannah
|
|
|
Luke Phone #: ###-#### second floor ok to occ 4th floor ok to cover
|
FIRE-Final Inspection | 5/13/2016 | 5/16/2016 | 5/16/2016 | A | PART |
Jim Page
|
|
|
2nd level fire life safety pased/complete.
|
BLD-Wall cover | 5/5/2016 | 5/6/2016 | 5/9/2016 | P | PART |
Dave Hannah
|
|
|
Luke Phone #: ###-#### thrid floor lids and part of fouth floor insulation ok
|
BLD-Energy code compliance | 5/3/2016 | 5/4/2016 | 5/4/2016 | P | PART |
Dave Hannah
|
|
|
Luke Phone #: ###-#### 3rd floor ok
|
BLD-Wall cover | 5/3/2016 | 5/4/2016 | 5/4/2016 | P | PART |
Dave Hannah
|
|
|
Luke Phone #: ###-#### 2nd floor ok
|
BLD-Energy code compliance | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | PART |
Dave Hannah
|
|
|
Luke Phone #: ###-#### ok to cover secobnd floor
|
BLD-Conference | 4/28/2016 | 5/2/2016 | 5/2/2016 | A | PART |
Dave Hannah
|
|
|
Nate Phone #: ###-#### ok to insulate floors
|