BLD-Final | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####. All issues were resolved.
|
DOC - Permit Finaled | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | FAIL |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Needs blower door test. Provide code compliant handrail on stairs to bonus room.
|
BLD-Energy code compliance | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 9/6/2016 | 9/7/2016 | 9/7/2016 | A | PASS |
Mike Jordan
|
|
|
Call before going there // Bob Phone #: ###-####. Corrections made. OK to insulate.
|
BLD-Framing/Rough-in | 9/2/2016 | 9/2/2016 | 9/6/2016 | P | NR |
Jim Sly
|
|
|
Bob Phone #: ###-#### need Mech insp.....need appr plans......attic ventil,,,,,, C/N posted.
|
BLD-Framing/Rough-in | 9/2/2016 | 9/6/2016 | 9/6/2016 | P | CANC |
Mike Jordan
|
|
|
Bob Phone #: ###-####
|
BLD-Wall Bracing | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PASS |
Phil Shearer
|
|
|
Shear // Bob Phone #: ###-####
|
BLD-Wall Bracing | 7/12/2016 | 7/13/2016 | 7/13/2016 | A | NR |
Jim Sly
|
|
|
Shear // Bob Phone #: ###-#### Framer to re-visit all brace panels and nail per plan.
|
BLD-Wall Bracing | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | FAIL |
Phil Shearer
|
|
|
Phone #: ###-####. Straps and hold downs
|
BLD-Foundation | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | PASS |
Phil Shearer
|
|
|
Derrick Phone #: ###-####
|
BLD-Foundation | 6/6/2016 | 6/7/2016 | 6/7/2016 | A | FAIL |
Mike Jordan
|
|
|
Request around 10:30 please, Derek Phone #: ###-####. Footing in several areas only 4 inches thick. these areas to be replaced.
|
BLD-Footing | 6/3/2016 | 6/3/2016 | 6/3/2016 | P | PASS |
Phil Shearer
|
|
|
Derek Phone #: ###-####
|