BLD-Final | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Jim Sly
|
|
|
Ian Phone #: ###-#### OK for Perm Occ.
|
BLD-Aging Inspection | 3/14/2017 | 3/14/2017 | 3/16/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Final | 1/12/2017 | 1/13/2017 | 1/13/2017 | P | PART |
Jim Sly
|
|
|
JC Phone #: ###-#### OK for Temp occ. OK for Perm Occ when Zoning signs off.
|
BLD-Final | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### OK for Temp Occ. OK for Perm. Occ. when Mech. permit finaled.
|
BLD-Final | 11/9/2016 | 11/10/2016 | 11/10/2016 | A | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### OK for Temp Occ. OK for perm Occ when all required finals sign for Perm Occ.
|
FIRE-Final Inspection | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 11/8/2016 | 11/9/2016 | 11/9/2016 | A | CANC |
Troy Cobbley
|
|
|
Jake Phone #: ###-####
|
FIRE-Final Inspection | 11/4/2016 | 11/7/2016 | 11/7/2016 | P | NR |
Troy Cobbley
|
|
|
Jake and I spoke about the need for emergency lights
|
BLD-Framing/Rough-in | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-####
|
FIRE-Final Inspection | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final inspection. I met with the general contractor and went over required life safety requirements to get this building signed off while others are unfinished. The biggest issue will be fire dpt access. I degerred him to Scott for temporary approval of fire lanes.
Jake Phone #: ###-####
|
BLD-Foundation | 8/29/2016 | 8/29/2016 | 8/29/2016 | P | PASS |
Jim Sly
|
|
|
Milton Phone #: ###-#### OK pending Special inspection, tests and approvals.
|