Permit Information
Permit NumberBLD16-01501
StatusFinaled
Name RRC CONTRACTORS
Site Address 877 W MAIN ST Unit: 700
Project NameOppenheimer Co. - Suite 700
Customer Number 
ePlanReviewYes
Description
** (OPPENHEIMER COMPANIES, INC- Wells Fargo Center Building- 7th Floor - Suite 700) ** Permit to remodel 9,961 sq. ft. within the 7th story of an existing 11 story high-rise building. Approval is contingent upon adhering to the approved plans on file. Work to include: removal and replacement select acoustic ceiling grid/tile, new lighting fixtures, electrical work. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/25/20167/25/20167/26/2016PPASS
DetailsDave Hannah
Zack Phone #: ###-####
DOC - Permit Finaled7/26/20167/26/20167/26/2016PPASS
DetailsDave Hannah
FIRE-Final Inspection7/25/20167/25/20167/25/2016PPASS
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
BLD-Ceiling Grid Inspection7/20/20167/20/20167/20/2016PPASS
DetailsDave Hannah
Zack Phone #: ###-####
BLD-Ceiling Grid Inspection7/14/20167/15/20167/14/2016APASS
DetailsDave Hannah
Zack Phone #: ###-####
BLD-Ceiling Grid Inspection7/13/20167/13/20167/14/2016PPASS
DetailsDave Hannah
Zack Phone #: ###-####
FIRE-Final Inspection7/11/20167/11/20167/11/2016PCANC
DetailsJim Page
Inspection request cancelled per conversation with Zack
BLD-Ceiling Grid Inspection7/8/20167/8/20167/10/2016PPART
DetailsDave Hannah
Zack Phone #: ###-#### phase two ok to cover
BLD-Conference6/23/20166/24/20166/24/2016APASS
DetailsMike Jordan
Zack Phone #: ###-####
FIRE-Conference6/23/20166/24/20166/24/2016ADONE
DetailsJim Page
Fire conference complete, discussed area's that would be acceptable to cover with ceiling tile.
BLD-Ceiling Grid Inspection6/16/20166/16/20166/16/2016PPART
DetailsDave Hannah
Zach Phone #: ###-#### phase one ok to cover
BLD-Conference6/16/20166/16/20166/16/2016PDONE
DetailsDave Hannah
Zach Phone #: ###-####