BLD-Final | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | PASS |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. I discussed with the general contractor about the racks, including the vertical and horizontal portions can not be over 8'. He was going to have the racks modified prior to a building inspection.
|
FIRE-Final Inspection | 10/13/2016 | 10/14/2016 | 10/14/2016 | P | FAIL |
Troy Cobbley
|
|
|
The project is not ready for a final yet. Need doors and hardware and fire extinguishers. Exit signs and emergency lights tested ok. Smoke evac tested ok. I spoke to the contractor about the racking over 8'.
|
FIRE-Alarm Testing | 10/13/2016 | 10/14/2016 | 10/14/2016 | A | DONE |
Troy Cobbley
|
|
|
The smoke evac system testing passed.
|
BLD-Framing/Rough-in | 10/2/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Mike Jordan
|
|
|
Call prior to going Phone #: 8035438600 >> Inspection requested via mobile web by Kevin Beachum. torefront framing ok. Also noted that cloud and air jhandler are now supported from top chords.
|
BLD-Framing/Rough-in | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | PART |
Mike Jordan
|
|
|
Call prior to going Phone #: 8035438600 >> Inspection requested via mobile web by Kevin. INterior steel stud framed walls, columns and hardlids ok. Noted that a racking permit is required. Also noted that cloud and air handling unit must be supported from the top chord or provide engineering.
|
BLD-Framing/Rough-in | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | NR |
Mike Jordan
|
|
|
Call prior to going Phone #: 8035438600 >> Inspection requested via mobile web by Kevin
|