BLD-Aging Inspection | 2/24/2017 | 2/24/2017 | 2/24/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Tony Young
|
|
|
Zack Phone #: ###-####,, garage ok
|
BLD-Framing/Rough-in | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PART |
Phil Shearer
|
|
|
Zach Phone #: ###-####. Hold downs
|
BLD-Wall Bracing | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PART |
Dave Hannah
|
|
|
Zach Phone #: ###-#### on garage ok to cover ext walls but needs to install holddown on each side of garage door
|
BLD-Final | 9/21/2016 | 9/22/2016 | 9/22/2016 | P | CANC |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
BLD-Footing | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | PART |
Tony Young
|
|
|
zach - early as possible Phone #: ###-####,, garage footings ,, work in progress,, ok
|
BLD-Energy code compliance | 7/13/2016 | 7/14/2016 | 7/14/2016 | P | PASS |
Tony Young
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PASS |
Tony Young
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 7/12/2016 | 7/13/2016 | 7/13/2016 | A | PASS |
Tony Young
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 7/12/2016 | 7/12/2016 | 7/12/2016 | P | NR |
Tony Young
|
|
|
Zack Phone #: ###-####,, needs mech passed
|
BLD-Framing/Rough-in | 7/11/2016 | 7/12/2016 | 7/12/2016 | A | NR |
Tony Young
|
|
|
Call before // Zack Phone #: ###-####,,, needs mechanical 1st
|
BLD-Framing/Rough-in | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | NR |
Tony Young
|
|
|
Call before // Zack Phone #: ###-####,, needs mechanical r/in,, ok to start insulation in walls
|
BLD-Footing | 6/9/2016 | 6/9/2016 | 6/9/2016 | P | PART |
Tony Young
|
|
|
Zack Phone #: ###-####- stepped footings ok
|
BLD-Footing | 6/8/2016 | 6/9/2016 | 6/9/2016 | A | NR |
Tony Young
|
|
|
Zack Phone #: ###-####-wuld like early pm
|
BLD-Footing | 6/7/2016 | 6/8/2016 | 6/8/2016 | P | NR |
Tony Young
|
|
|
Zack Phone #: ###-####-wuld like early pm
|
BLD-Foundation | 6/3/2016 | 6/3/2016 | 6/3/2016 | P | PART |
Tony Young
|
|
|
Phone #: ###-####,, tall walls work in progress,, ok to pour when ready
|
BLD-Foundation | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | NR |
Mike Jordan
|
|
|
Zack Phone #: ###-####,, late am
|
BLD-Footing | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | PART |
Tony Young
|
|
|
Zack Phone #: ###-####,, ftgs ok now,, ok to pour
|
BLD-Footing | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | FAIL |
Dave Hannah
|
|
|
Zack Phone #: ###-#### not to plans
|