BLD-Final | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ.
|
DOC - Permit Finaled | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Mike Jordan
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
BLD-Final | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | PASS |
Mike Jordan
|
|
|
Late morning - Doug Phone #: ###-####
|
BLD-Final | 9/12/2017 | 9/13/2017 | 9/13/2017 | A | PASS |
Mike Jordan
|
|
|
Temp Occupancy-Herb Phone #: ###-####. Temp occ granted at this time. Will be ok for perm occ. once zoning and public works has signed perm.occ.
|
BLD-Final | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | CANC |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 9/8/2017 | 9/11/2017 | 9/11/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Conference | 9/7/2017 | 9/7/2017 | 9/7/2017 | P | PEND |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Needs zoning and public works.
|
FIRE-Final Inspection | 9/7/2017 | 9/7/2017 | 9/7/2017 | P | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given until the project related fire alrm permit has been finaled and the fire dept access signage is provided and NFPA signage at the Oxygen Room door. Herb provided what appears to be compliant hardware for the Kitchen door.
Herb Phone #: ###-####
|
FIRE-Conference | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | DONE |
Troy Cobbley
|
|
|
Performed the rest of the life safety today. I need the project related fire alarm pemit finaled, NFPA signs for the oxygen room, provide fire dept access signage at the south entrance.
|
FIRE-Conference | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | DONE |
Troy Cobbley
|
|
|
Started on life safety this morning. We tested exit signs and emergency lighting. I noted the two Garden area devices did not function. On a afternoon return trip the electrician had repaired the devices. No other items have been inspected yet since the bulk of time has been spent on the project related fire alarm permit.
|
FIRE-Final Inspection | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | CANC |
Troy Cobbley
|
|
|
Herb Phone #: ###-####
|
BLD-Conference | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | NR |
Jim Sly
|
|
|
Herb Phone #: ###-####
|
BLD-Final | 8/31/2017 | 9/1/2017 | 9/1/2017 | P | CANC |
Brandon Shaw
|
|
|
Herb Phone #: ###-####
|
FIRE-Final Inspection | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was just for a conference for the center portion of the building. I noted acouple of smoke detectors with issues.
Herb Phone #: ###-####
|
FIRE-Conference | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | DONE |
Troy Cobbley
|
|
|
Herb, myself and Mike Jordan did a courtesy walk through one the north and south thirds of the building. I noted missing notificaton devices and two strobes overspaced.
Phone #: ###-####
|
BLD-Conference | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 8/16/2017 | 8/16/2017 | 8/16/2017 | A | PART |
Mike Jordan
|
|
|
walk through for final on north and south wings rooms only.
|
BLD-Energy code compliance | 7/17/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Remainder of canlight protection and exterior walls in central great room ok.
|
FIRE-Conference | 7/12/2017 | 7/12/2017 | 7/12/2017 | A | DONE |
Katie Marron
|
|
|
Phone Call with K2 Construction on occupant load signs and how only one per assembly room/space is required.
|
BLD-Other | 7/11/2017 | 7/11/2017 | 7/11/2017 | P | PART |
Mike Jordan
|
|
|
Work in progress on providing 2 layers of 5/8 type x rock on can lights in horizontal roof/ceiling assembly.
|
BLD-Other | 7/10/2017 | 7/11/2017 | 7/11/2017 | A | NR |
Mike Jordan
|
|
|
fire damping- round 12pm- Herb Phone #: ###-####.
|
BLD-Framing/Rough-in | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 6/28/2017 | 6/28/2017 | 6/28/2017 | A | PASS |
Mike Jordan
|
|
|
5/8 type x sheet rock wraps for 1hr. protection on columns and beams in central great room.
|
BLD-Framing/Rough-in | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Other | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PART |
Brandon Shaw
|
|
|
Fire proofing // Herb Phone #: ###-#### Can lights in gathering rooms 3&4- two layer Ceiling @ shower furr outs Rm- 131, 132, 135, 136, 130, & 127- two layers.
|
BLD-Framing/Rough-in | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PART |
Mike Jordan
|
|
|
Herb Phone #: ###-####
|
BLD-Framing/Rough-in | 5/31/2017 | 5/31/2017 | 5/31/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/31/2017 | 5/31/2017 | 5/31/2017 | A | PASS |
Mike Jordan
|
|
|
Can lights at south half of building know has 2layers of 5/8type x rock for roof/ceiling assembly, ok. north soffits double layer of 5/8 type x ok.
|
BLD-Framing/Rough-in | 5/23/2017 | 5/24/2017 | 5/24/2017 | P | PART |
Mike Jordan
|
|
|
2hr. fire barrier wall at east wing at parpet has been repaired ok. Smoke barrier wall above ceiling ok. Noted the can lights only have 1 layer of 5/8 type x rock around them in roof/ceiling assembly. Two layers are required or an UL listed and approved cover.
|
BLD-Conference | 5/23/2017 | 5/24/2017 | 5/24/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 5/23/2017 | 5/24/2017 | 5/24/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Rooms 103 to 111 and rooms120 to 123.
|
BLD-Framing/Rough-in | 5/24/2017 | 5/24/2017 | 5/24/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Rooms 103 to 111 and rooms 120 to to123.
|
BLD-Framing/Rough-in | 5/10/2017 | 5/17/2017 | 5/17/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/10/2017 | 5/17/2017 | 5/17/2017 | A | PART |
Mike Jordan
|
|
|
!hr soffit at east side of building complete and ok. 2hr . fire wall above ceiling east and west wings needs to have penetrations removed at roof deck within the 4ft. Smoke barrier west wing above ceiling needs to firestop sprinkler pipe.
|
BLD-Framing/Rough-in | 5/3/2017 | 5/10/2017 | 5/10/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/3/2017 | 5/10/2017 | 5/10/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/1/2017 | 5/3/2017 | 5/3/2017 | A | PASS |
Mike Jordan
|
|
|
Rated exterior soffits at south and south-east areas of building ok.
|
BLD-Framing/Rough-in | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | PASS |
Mike Jordan
|
|
|
Exterior shear walls ok.
|
BLD-Wall Bracing | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | PASS |
Mike Jordan
|
|
|
exterior wall bracing ok.
|
BLD-Framing/Rough-in | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | NR |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Rooms 113 to 119 ok.
|
BLD-Framing/Rough-in | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Rooms 113 to 119 ok.
|
BLD-Other | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | PASS |
Mike Jordan
|
|
|
smoke wall insp// Herb Phone #: ###-####. Smoke barrier, east wing abve ceiling grid ok.
|
BLD-Framing/Rough-in | 4/25/2017 | 4/26/2017 | 4/26/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Rooms 127 to 133 ok.
|
BLD-Framing/Rough-in | 4/25/2017 | 4/25/2017 | 4/25/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Rooms 127 to 13 ok.
|
BLD-Framing/Rough-in | 4/19/2017 | 4/20/2017 | 4/20/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/18/2017 | 4/19/2017 | 4/19/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/19/2017 | 4/19/2017 | 4/19/2017 | P | PASS |
Mike Jordan
|
|
|
Exterior walls at south wing and east wing south half.
|
BLD-Conference | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/4/2017 | 4/5/2017 | 4/5/2017 | P | PART |
Mike Jordan
|
|
|
Framing inspection on south wing rooms and east wing rooms,South half. Needs to complete all lateral bracing, nail off all simpson hangars, provide additional studs and squash blocking under 2ply girder bearing. Complete the idividual encasement for 1 hr. protection on columns and complete all fire caulking. Work is still in progress in these areas. All rough ins except for electrical have been completed. Aslo Needs to provide the sheetrock at ceiling in concealed areas for 1hr. roof/ceiling assembly.
|
BLD-Framing/Rough-in | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | PASS |
Mike Jordan
|
|
|
Remaining roof nailing completed and ok to cover.
|
BLD-Framing/Rough-in | 4/4/2017 | 4/5/2017 | 4/5/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Mike Jordan
|
|
|
Roof nailing around courtyard #1 ok.
|
BLD-Wall Bracing | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | NR |
Mike Jordan
|
|
|
Herb Phone #: ###-####. roof nailing, moved to pm. inspection.
|
BLD-Other | 3/8/2017 | 3/9/2017 | 3/9/2017 | A | PASS |
Mike Jordan
|
|
|
Roof nailing - Herb Phone #: ###-####. North wing, south side ok to cover.
|
BLD-Framing/Rough-in | 3/3/2017 | 3/6/2017 | 3/6/2017 | P | PASS |
Mike Jordan
|
|
|
Herb//this is for shear nailing roof Phone #: ###-####. Roof nailing north wing and north west wing. Nailing edge nailing and nailing on drag trusses ok.
|
BLD-Footing | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PART |
Jim Sly
|
|
|
Herb Phone #: ###-#### Thickened footings at slab. OK pending Geotech special inspections, tests and approvals.
|
BLD-Final | 2/2/2017 | 2/3/2017 | 2/3/2017 | A | CANC |
Mike Jordan
|
|
|
Herb Phone #: ###-#### **not sure this should be a final. herb said roof, but didn't sound too sure**
|
BLD-Framing/Rough-in | 2/3/2017 | 2/3/2017 | 2/3/2017 | A | PASS |
Mike Jordan
|
|
|
Herb Phone #: ###-#### **not sure this should be a final. herb said roof, but didn't sound too sure**. Roof nailing ok.
|
BLD-Framing/Rough-in | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PART |
Mike Jordan
|
|
|
Work in progress on roof sheeting.
|
BLD-Ceiling Grid Inspection | 1/13/2017 | 1/17/2017 | 1/17/2017 | A | CANC |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Moved to pm.
|
BLD-Other | 1/11/2017 | 1/12/2017 | 1/12/2017 | P | PASS |
Mike Jordan
|
|
|
Herb-roof nailing scheduling Phone #: ###-####. South east portion ok.
|