FIRE-Final Inspection | 10/11/2017 | 10/12/2017 | 10/11/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | CANC |
Troy Cobbley
|
|
|
Opticon was non-functional.
Tim Sanders Phone #: ###-####
|
BLD-Final | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Mike Jordan
|
|
|
Tim Sanders Phone #: ###-####. Ok for temp. occ. will be ok for perm occ. once fire/life/safety and zoning signs perm.
|
BLD-Final | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | NR |
Mike Jordan
|
|
|
Tim Phone #: ###-####. Needs elctrical final.
|
FIRE-Final Inspection | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
FIRE-Final Inspection | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | FAIL |
Troy Cobbley
|
|
|
need building number, site address and small documents
|
BLD-Foundation | 10/25/2016 | 10/25/2016 | 10/25/2016 | P | PASS |
Mike Jordan
|
|
|
Scott-rebar-pour time 3:00 Phone #: ###-####
|