BLD-Final | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 1/9/2017 | 1/9/2017 | 1/9/2017 | P | FAIL |
Jim Storey
|
|
|
Mark Phone #: ###-#### saftey glazing verifaction
|
BLD-Final | 12/7/2016 | 12/7/2016 | 12/7/2016 | P | PART |
Jim Storey
|
|
|
would like call ahead; Justin Phone #: ###-#### temp ok pending glazzing and ele
|
FIRE-Final Inspection | 12/7/2016 | 12/7/2016 | 12/7/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, one fire extinguisjer is in place, the other will be mounted in discussed location, both have current inspection tags. Final life fire safety inspection passed/complete.
|
FIRE-Conference | 12/7/2016 | 12/7/2016 | 12/7/2016 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
FIRE-Conference | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | CANC |
Jim Page
|
|
|
Fire conference rescheduled for 10AM 07DEC16 per conversation with Mark Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/14/2016 | 11/15/2016 | 11/15/2016 | P | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### pending others
|
BLD-Ceiling Grid Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | NR |
Mike Jordan
|
|
|
Mark Phone #: ###-####. Needs MEP inspections first.
|
BLD-Framing/Rough-in | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Jim Storey
|
|
|
Mark Phone #: ###-#### frame ok to cover/ 12 aprotch door to be checked at final.
|