BLD-Final | 1/3/2017 | 1/6/2017 | 1/6/2017 | A | PASS |
Dave Hannah
|
|
|
Leslie Phone #: ###-####
|
DOC - Permit Finaled | 1/6/2017 | 1/6/2017 | 1/6/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | PEND |
Dave Hannah
|
|
|
Leslie Phone #: ###-#### ok to insulate after other trades are completed and rough in spections done
|
BLD-Wall Bracing | 10/10/2016 | 10/11/2016 | 10/11/2016 | A | PASS |
Tony Young
|
|
|
Russell// inspection for siding Phone #: ###-####
|
BLD-Other | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Tony Young
|
|
|
Russell// inspection for siding Phone #: ###-####
|
BLD-Foundation | 9/30/2016 | 10/3/2016 | 10/3/2016 | P | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, addition footing ok,, work in progress
|