BLD-Final | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Dillon Barresi
|
DOC - Permit Finaled | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 1/15/2020 | 1/15/2020 | 1/15/2020 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 9/3/2019 | 9/3/2019 | 9/3/2019 | | PASS |
Jim Storey
|
|
|
Expires: 10/19/19
|
BLD-Framing/Rough-in | 4/18/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Jim Storey
|
|
|
steel stud framing // Paul Phone #: ###-#### south west wall framing ok fab walls
|
BLD-Conference | 4/3/2019 | 4/3/2019 | 4/3/2019 | A | PEND |
Jim Storey
|
|
|
Expires: 01/09/19
|
BLD-Aging Inspection | 7/13/2018 | 7/13/2018 | 7/13/2018 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 3/1/2018 | 3/1/2018 | 3/1/2018 | | PASS |
Jim Storey
|
|
|
ncfi wip
|
BLD-Aging Inspection | 10/18/2017 | 10/18/2017 | 10/18/2017 | | PASS |
Jim Storey
|
|
|
wip ncfi
|
BLD-Framing/Rough-in | 6/27/2017 | 6/28/2017 | 6/27/2017 | A | CANC |
Jim Storey
|
|
|
Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 6/5/2017 | 6/6/2017 | 6/6/2017 | A | PART |
Jim Storey
|
|
|
Ken-2 hour assemblies Phone #: ###-####air ok center shaft wall ok wip/ north wall of 50 pirlin atchment to studs ok/ elavator walls ok/ south east st ok to complet.
|
BLD-Framing/Rough-in | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | PASS |
Jim Storey
|
|
|
Contact Jake Turnbough to look at the exterior framing on the west side of the building. Phone #: ###-#### Inspection requested via web by Jeremy Richardson stair wall/elavator exterior wall ok
|
BLD-Framing/Rough-in | 5/9/2017 | 5/9/2017 | 5/9/2017 | P | FAIL |
Jim Storey
|
|
|
c/n provide headers requred for return air wall penatrations not on plan for load and deflection// need engenery report to verrify exterior foam insulation.
|
BLD-Framing/Rough-in | 4/10/2017 | 4/11/2017 | 4/11/2017 | A | FAIL |
Jim Storey
|
|
|
Ken Phone #: ###-#### wall defeltion stud removal at duct pentrations/ fire stopping listings from all trades for penatrating idems and rattings, type of matrial used/door listings and aplactions 3 hr/ gyp to concrete rated joints.
|
BLD-Framing/Rough-in | 3/17/2017 | 3/20/2017 | 3/20/2017 | A | PASS |
Jim Storey
|
|
|
Ken Phone #: ###-#### random areas
|
BLD-Framing/Rough-in | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | CANC |
Mike Jordan
|
|
|
Interior framing, call ahead for access - Ben Phone #: ###-####. Moved to Monday per contractor.
|
BLD-Framing/Rough-in | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | PASS |
Jim Storey
|
|
|
Ken Phone #: ###-#### level 10 29-32/ab tgm,com ok //level 20 polish rm ok
|
BLD-Conference | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | DONE |
Jim Storey
|
|
|
Ken Phone #: ###-####
|
BLD-Conference | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | PART |
Jim Storey
|
|
|
Talk about the roof parapet cap on non rated walls. Contact Neal Mays Phone #: ###-#### Inspection requested via web by Jeremy Richardson fire treated required
|
BLD-Framing/Rough-in | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | CANC |
Mike Jordan
|
|
|
Ken Phone #: ###-####
|
BLD-Conference | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | CANC |
Dave Hannah
|
|
|
Talk about the roof parapet cap on non rated walls. Contact Neal Mays Phone #: ###-#### Inspection requested via web by Jeremy Richardson
|
BLD-Framing/Rough-in | 1/31/2017 | 1/31/2017 | 1/31/2017 | P | PASS |
Jim Storey
|
|
|
Ken Phone #: ###-#### riser rm 10/office space 10 walls ok/east interior sheet metal ok
|
BLD-Wall cover | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | PART |
Jim Sly
|
|
|
South wall framing for wall cover contact Neal Mays Phone #: ###-#### Inspection requested via web by Jeremy Richardson South Exterior wall.....Level 30 OK. East 1/2 of South Exterior wall.....Level 20........OK.
|
BLD-Framing/Rough-in | 1/20/2017 | 1/23/2017 | 1/23/2017 | A | PART |
Jim Storey
|
|
|
Ken Phone #: ###-#### wall cover ok at level 10 1819 tg/ c/n s line provide detail for sline/u.817.8 details for firewall and colum protection
|
BLD-Other | 1/16/2017 | 1/17/2017 | 1/18/2017 | A | PART |
Dave Hannah
|
|
|
CMU wall and re bar before wall is filled with concrete. Phone #: ###-#### Inspection requested via web by Christophe Haynes talked with contractor he will get spec inspection on rebar and grouting
|
BLD-Conference | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PART |
Jim Storey
|
|
|
stock office 130 meetting recieved ul listing/ walked job with stock/ pending resolve to design isues at beams and colums in 2hr north wall/ vert protection at bearing in fab to be fixed/ stair enclosers framing defencies pointed out to stock.
|
BLD-Framing/Rough-in | 1/12/2017 | 1/13/2017 | 1/13/2017 | A | PASS |
Jim Storey
|
|
|
Framing inspection for the South West stair. Contact Neal Mays Phone #: ###-#### Inspection requested via web by Jeremy Richardson
|
BLD-Other | 12/29/2016 | 12/29/2016 | 12/30/2016 | P | PASS |
Jim Storey
|
|
|
Water proofing // James Phone #: ###-#### south east penatrations ok
|
BLD-Framing/Rough-in | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | PART |
Jim Storey
|
|
|
Ken Phone #: ###-#### sub mit listing for 2 hr wall/ colums in 2 hr wall not per plan rfi as to how to build./colum screw sch. 12 max/ expation joint in 2hr wall and concrete wall needed prior to instalation.
|
BLD-Wall cover | 12/22/2016 | 12/23/2016 | 12/23/2016 | A | NH |
Jim Storey
|
|
|
Ken Phone #: ###-#### no reply
|
BLD-Framing/Rough-in | 12/22/2016 | 12/23/2016 | 12/23/2016 | A | NH |
Jim Storey
|
|
|
Ken Phone #: ###-#### no reply
|
BLD-Framing/Rough-in | 12/21/2016 | 12/21/2016 | 12/21/2016 | P | PART |
Dave Hannah
|
|
|
Ken Phone #: ###-#### basement level wall on grid line s.5 18thru 34 ok to insulate also note 2hr ext fire wall west wall ext done by isi on int by forety int wall still need to see ul listing screw paterion on first layer is 12 oc stager on sec lay ok
|
BLD-Framing/Rough-in | 12/16/2016 | 12/20/2016 | 12/20/2016 | A | FAIL |
Jim Storey
|
|
|
Wall framing inspection Contact Neal Mays Phone #: ###-#### Inspection requested via web by Jeremy Richardson c/n BO to review rated 2hr wall covered with out permit and insp. as to how to poceed/ need listing being used submited/rfi from engineer for bearing double stud kings leg cut off west pass thru./ need determanation as to non fire treated wood installed in roof per aproved plan.
|
BLD-Framing/Rough-in | 12/8/2016 | 12/9/2016 | 12/9/2016 | A | FAIL |
Jim Storey
|
|
|
Framing for cover contact Neal Mays ay ###-#### Phone #: ###-#### Inspection requested via web by Jeremy Richardson no aproved plan on site and docs.
|