Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD16-03993
StatusIssued
Name FIRST CONGREGATIONAL CHURCH OF BOI
Site Address 2201 W WOODLAWN AVE
Project NameFirst Congrerational Church
Customer Number 
ePlanReviewNo
Description
(FIRST CONGREGATIONAL CHURCH OF BOISE) Pernit for minor tenant improvements to the to the existing lounge area and the existing entry doors with work to include the construction of some Interior walls (less than 60 lineal feet) to create a new pastors office and a new church office. The Entry doors are being modified to add automatic controls to increase the accessiblity of the entrancce. The modification results in a decrease in the occupant load in this area of 38 occupnant resulting in this area changing from an A-3 to a B occupancy. All existing rated construction at the main entry/lobby area is to remain unaltered. All finishes to comply with chapter 8 of the IBC. All work to be per the approved plans
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection11/17/201711/17/201711/17/2017 PEND
DetailsDave Hannah
BLD-Aging Inspection6/29/20176/29/20177/6/2017 PASS
DetailsDave Hannah
BLD-Framing/Rough-in2/13/20172/14/20172/14/2017PPASS
DetailsDave Hannah
Roger Phone #: ###-####
BLD-Framing/Rough-in2/6/20172/6/20172/6/2017PPEND
DetailsDave Hannah
Roger Phone #: ###-#### framing ok but need the elec rough in