BLD-Final | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PASS |
Jim Sly
|
|
|
Please call Jared 1/2 hr prior at ###-#### Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
DOC - Permit Finaled | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 3/28/2017 | 3/28/2017 | 3/28/2017 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner Need Fire Final and Final Letter of Approval from Special Insp Agency.
|
FIRE-Final Inspection | 3/28/2017 | 3/28/2017 | 3/28/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Footing | 12/20/2016 | 12/21/2016 | 12/21/2016 | A | FAIL |
Jim Sly
|
|
|
Please call Jared at ###-#### 1/2 hr before inspection. Requested inspection time after 10 am. Phone #: ###-#### Inspection requested via web by Jared Waggoner Requires special inspection.....3,000 to 4,000 psi concrete. Plans were not stamped approved. cannot pour without forms and subgrade at min. 35 degrees. Cannot pour without external heat source. "cold Weather conditions" three consecutive days will be less than 40 degrees. last night 18 degrees.....next three days 21-10 24-18 26-20. Need to maintain min. 50 degrees for min. 3 days. above per ACI 306 standard for cold weather concrete.
|