DOC - Permit Finaled | | | 9/14/2018 | | DONE |
|
|
|
this permit for foundation only. Ref Bld16-03292 for complete garage project
|
BLD-Foundation | 3/3/2017 | 3/8/2017 | 3/10/2017 | A | PASS |
Dave Hannah
|
|
|
Robert Phone #: ###-####
|
BLD-Foundation | 3/3/2017 | 3/3/2017 | 3/3/2017 | P | PEND |
Dave Hannah
|
|
|
Robert Phone #: ###-#### slab on grade ok to place after spec insp signoff
|
BLD-Foundation | 2/21/2017 | 2/22/2017 | 2/23/2017 | P | PEND |
Dave Hannah
|
|
|
Robert-rebar Phone #: ###-#### ok after spec insp sign off
|
BLD-Foundation | 2/9/2017 | 2/10/2017 | 2/10/2017 | A | PASS |
Dave Hannah
|
|
|
Rebar , slab on grade // Robert Phone #: ###-####
|
BLD-Footing | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | PEND |
Dave Hannah
|
|
|
Rebar - Robert Phone #: ###-#### ok after mti signoff
|
BLD-Concrete | 1/27/2017 | 1/27/2017 | 1/30/2017 | P | PEND |
Dave Hannah
|
|
|
Rebar // Robert Phone #: ###-#### ok after mti signoff
|
BLD-Foundation | 1/26/2017 | 1/27/2017 | 1/27/2017 | A | CANC |
Dave Hannah
|
|
|
Rebar // Robert Phone #: ###-####
|
BLD-Foundation | 1/19/2017 | 1/20/2017 | 1/20/2017 | A | PEND |
Dave Hannah
|
|
|
Rebar // Robert Phone #: ###-#### final aproval will be signed off by spec inspection
|
BLD-Foundation | 1/4/2017 | 1/5/2017 | 1/5/2017 | P | PEND |
Dave Hannah
|
|
|
Rebar // Robert Phone #: ###-#### pours pushed bak to monday
|
BLD-Foundation | 12/19/2016 | 12/20/2016 | 12/20/2016 | P | PASS |
Dave Hannah
|
|
|
Rebar // Robert Phone #: ###-####
|
BLD-Foundation | 12/14/2016 | 12/15/2016 | 12/16/2016 | P | PEND |
Dave Hannah
|
|
|
Rebar // Robert Phone #: ###-#### ok after mti final sign off
|
BLD-Footing | 12/9/2016 | 12/9/2016 | 12/9/2016 | A | PASS |
Dave Hannah
|
|
|
Robert- Phone #: ###-####
|
BLD-Footing | 12/6/2016 | 12/8/2016 | 12/9/2016 | P | PASS |
Dave Hannah
|
|
|
Robert- Phone #: ###-####
|
BLD-Footing | 12/6/2016 | 12/7/2016 | 12/7/2016 | P | PASS |
Dave Hannah
|
|
|
Robert-Phone #: ###-####
|