DOC - Permit Finaled | | | 1/18/2019 | | DONE |
|
|
|
Per passing final inspection 5/31/18 by Jim Sly
|
BLD-Final | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Jim Sly
|
|
|
Nick Phone #: ###-#### PUBLIC WORKS........ZONING........signed off on GRD Permit??
|
BLD-Final | 5/18/2018 | 5/21/2018 | 5/21/2018 | A | PEND |
Jim Sly
|
|
|
This is Ken Barr with ESI. I am filling in for Chris while he is on vacation. Thank you, Phone #: ###-#### Inspection requested via web by Chris Palmer Need Perm Occ. status on 3 Permits .....MEC 17- 01556, PLM- 17-03877, and PLM 17- 01432
|
BLD-Final | 4/19/2018 | 4/20/2018 | 4/20/2018 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer OK for Perm. Occ when Plumbing signs off Perm.
|
FIRE-Final Inspection | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed as per activity comments no sign off required. Fire hydrants and fire dept access reviewed under the Grading permit
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled.
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the Grading permit finaled and the fire sprinkler permit finaled.
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Concrete | 12/19/2017 | 12/20/2017 | 12/20/2017 | P | PART |
Jim Sly
|
|
|
rebar- Justin Phone #: ###-#### Above roof.....tower....OK pending MTI special inspections tests and approvals.
|
BLD-Foundation | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PART |
Jim Sly
|
|
|
Rebar // Dave Phone #: ###-#### MTI on site.
|
BLD-Other | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | PART |
Jim Sly
|
|
|
rebar // Dave Phone #: ###-#### STRATA on site.
|
BLD-Other | 8/24/2017 | 8/25/2017 | 8/28/2017 | P | PART |
Jim Sly
|
|
|
Reinforcing second level deck // Dave Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
BLD-Foundation | 5/22/2017 | 5/23/2017 | 5/23/2017 | P | PART |
Jim Sly
|
|
|
Rebar // Dave Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|