FIRE-Final Inspection | 6/4/2018 | 6/4/2018 | 6/4/2018 | P | PASS |
Jim Page
|
|
|
Previously noted items have been repaired, fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by the main entrance. Final life fire safety inspection is complete.
Please call when on site - Evan Phone #: ###-####
|
BLD-Final | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Jim Storey
|
|
|
Evan Phone #: ###-#### final ok pending others.
|
FIRE-Final Inspection | 5/30/2018 | 5/31/2018 | 5/31/2018 | P | FAIL |
Jim Page
|
|
|
Remaining item that must be completed before life fire safety inspection can be finaled is stairwells (stated in noted on 23MAY2018), stairwells must be 100% completed before life fire safety can be finaled, I spoke with Ron Johnson with Boise Fire and he agrees with staiwells being completed.
Lee Phone #: ###-####
|
BLD-Other | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Jim Storey
|
|
|
Lee---partial final Phone #: ###-#### bottom of trash shaft ok to cover
|
FIRE-Conference | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | DONE |
Jim Page
|
|
|
Fire conference complete.
Lee-- fire proofing--early as possible Phone #: ###-####
|
FIRE-Final Inspection | 5/23/2018 | 5/23/2018 | 5/23/2018 | P | FAIL |
Jim Page
|
|
|
Provide "No Roof Access" signage on northwest stairwell. Provide double sided exit signs by th 20 rooms (220, 320, 420 and 520). Fire sprinkler next to exhaust fan in trash room is obstructed. Provide electrical outlet covers that are missing on electrical outlets. Provide an "Emergency Evacuation Plan" for each apartment. Stairwells must be 100% completed before any occupancy. Adjust insulation next to sidewall sprinkler heads to maintain the 4 to 6 inches of vertical clearance that is required. Fire sprinkler heads in level 1 trash room that are painted must be replaced. Ceiling tile that is missing on level 1 must be installed for fire sprinkler heat collection. All fire sprinkler escutcheons need to be in place and installed correctly (no loose or hanging down escutcheons). FIR permits for fire sprinkler and fire alarm must be finaled before life fire safety can be completed.
Lee Scott Phone #: ###-####
|
BLD-Final | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PART |
Jim Storey
|
|
|
Partial final - lee Phone #: ###-####si and engineer sign off ok and archived/ drop ceillings ok
|
BLD-Wall cover | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### doors grouted ok/top of trash shoot and bottom ok to cover// need listing for heater box in trash encloser// pipe collors at podiem ok
|
BLD-Final | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | PART |
Jim Storey
|
|
|
Request 10am at same time Fire inspector will be there // partial final // Lee Scott Phone #: ###-#### all door above podiem ok forsmoke and latch per listing
|
FIRE-Final Inspection | 5/9/2018 | 5/11/2018 | 5/11/2018 | A | FAIL |
Jim Page
|
|
|
Level 1 doors on both stairwells need to have grouting installed for stairwell rating. South emergency exit for parking garage is interfaced with the access control, door cannot be access controled due to the door being the second emergency exit for the parking garage. Emergency exit signs need to be installed in discussed locations. Provide building fire and evacuation plans in each apartment unit per note number 11 of building permit fire code review noted.
Coordinated with Jim for 10am // Evan Phone #: ###-####
|
BLD-Conference | 5/9/2018 | 5/11/2018 | 5/11/2018 | A | CANC |
Dave Hannah
|
|
|
Request 10am // Evan Phone #: ###-####
|
BLD-Final | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | CANC |
Jim Storey
|
|
|
Lee Scott would like a partial final Phone #: ###-####
|
BLD-Final | 5/4/2018 | 5/4/2018 | 5/4/2018 | P | PART |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### 203 and mop closets
|
BLD-Final | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | DEFR |
Jim Storey
|
|
|
Lee Scott Phone #: ###-####
|
BLD-Other | 5/2/2018 | 5/3/2018 | 5/3/2018 | A | PASS |
Jim Storey
|
|
|
shaft board- lee Phone #: ###-####
|
BLD-Final | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PART |
Jim Storey
|
|
|
Area 2 & 3 - Lee Scott Phone #: ###-#### area 2 door closer fail//
|
BLD-Final | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | DEFR |
Jim Storey
|
|
|
Area 2 & 3 - Lee Scott Phone #: ###-#### out of time//
|
BLD-Final | 4/26/2018 | 4/27/2018 | 4/27/2018 | A | PASS |
Jim Storey
|
|
|
area 3 // Lee Scott Phone #: ###-####
area 2 ok need 2 and 3rd door adj one ea. floor// core board ceilling in progress ok
|
BLD-Wall cover | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### 4th floor ceilling patch ok/ storage rooms fire stopping in progress/ shaft patch ok to cover/ firedamper access signs ok
|
BLD-Final | 4/16/2018 | 4/17/2018 | 4/17/2018 | A | PASS |
Jim Storey
|
|
|
Partial Final - Evan Phone #: ###-#### doors ok area 3 to units/ storage rm firestopping required//4 floor ceilling needs reinsp. spk holes// fire smoke dampers need lables/ list w/ lee
|
BLD-Energy code compliance | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Brandon Shaw
|
|
|
Parking garage ceiling insulation
|
BLD-Framing/Rough-in | 3/26/2018 | 3/26/2018 | 3/26/2018 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### framing 1st floor area 3 and 1 ok to cover/ ceilling ok to cover same pending trades// parking garage ceilling ok to insulate.
|
BLD-Framing/Rough-in | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | CANC |
Jim Storey
|
|
|
Lee Phone #: ###-####
|
BLD-Energy code compliance | 3/7/2018 | 3/7/2018 | 3/7/2018 | P | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### exterior walls lobby 1st floor ok to cover.
|
BLD-Other | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PASS |
Jim Storey
|
|
|
shaft liner // Lee Scott Phone #: ###-#### stair lids and shafts in corridors ok to cover
|
BLD-Other | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Jim Storey
|
|
|
shaft insp // lee scott Phone #: ###-#### 4 and 3 ok/ corridor at ada showers on area 1
|
BLD-Framing/Rough-in | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | PASS |
Jim Storey
|
|
|
4th floor ceilling all but hvac at se stair
|
BLD-Framing/Rough-in | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PART |
Jim Storey
|
|
|
Lee Phone #: ###-#### backing at handrail/grab bars/ fire stopping stair encloser/exterior insulation/vapor barrior
|
BLD-Other | 2/26/2018 | 2/26/2018 | 2/26/2018 | P | CANC |
Jim Storey
|
|
|
Area 1, 1st fl - Lee Phone #: ###-#### 105 & 106 ok to cover
|
BLD-Other | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Jim Storey
|
|
|
3dr floor corridor ok
|
BLD-Other | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Jim Storey
|
|
|
fire caluking- Lee Phone #: ###-#### area 1# 2nd floor ok / 1st floor area 1 ok all but 105 & 106 nr
|
BLD-Other | 2/22/2018 | 2/22/2018 | 2/22/2018 | P | PART |
Jim Storey
|
|
|
Fire caulking, area 1 2nd & 3rd fl - Lee Phone #: ###-####
|
BLD-Other | 2/20/2018 | 2/21/2018 | 2/21/2018 | A | PART |
Dave Hannah
|
|
|
Lee-fire caulking Phone #: ###-#### corradors levels 1 and 2 0k to cover
|
BLD-Other | 2/14/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Jim Storey
|
|
|
Fire Caulking- Lee Phone #: ###-#### all drops ceillings in rooms area a third floor/ hold on 300 3rd nr
|
BLD-Other | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | PASS |
Jim Storey
|
|
|
fire coulking /// Lee scott Phone #: ###-#### fourth floor area a ok
|
BLD-Other | 2/12/2018 | 2/12/2018 | 2/12/2018 | P | CANC |
Jim Storey
|
|
|
Lee-fire caulking-area 1 3rd and 4th floors-would like as early as possibly Phone #: ###-#### //cancelled per Lee Scott 11:51am 12/12/18 leg
|
BLD-Conference | 2/7/2018 | 2/8/2018 | 2/8/2018 | A | PASS |
Jim Storey
|
|
|
Lee-Fire Caulking Phone #: ###-#### 300/trash rms 1,2,3,4th/storage rooms 1-4/area 2 420,423,425,432
|
BLD-Other | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | DEFR |
Jim Storey
|
|
|
Lee-Fire Caulking Phone #: ###-####
|
BLD-Framing/Rough-in | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Jim Storey
|
|
|
truss repair complet ok unit 403
|
BLD-Energy code compliance | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Jim Storey
|
|
|
Lee-area 1 & 2 multiple floors Phone #: ###-#### area 1 2nd floor mech rms ok 1,2,3,4,/ 105 ok /hd ok to cover/ stair 1 insulation ok to cover.
|
BLD-Other | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | NR |
Jim Storey
|
|
|
Lee-fire caulkings-area 1 & 2 multiple floors Phone #: ###-####
|
BLD-Energy code compliance | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | PASS |
Jim Storey
|
|
|
1st & 2nd floor area 1 - Lee Phone #: ###-#### 204/205/206// mech rm 3rd floor/mech shaft stair#2 ok
|
BLD-Energy code compliance | 2/1/2018 | 2/1/2018 | 2/2/2018 | P | DEFR |
Jim Storey
|
|
|
Lee Phone #: ###-####
|
BLD-Energy code compliance | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-####stair 1#/fire chalk 320/322/323/324/325/326/328/330/332// insulation 320/322/323/324/330/332/232/132
|
BLD-Wall cover | 1/29/2018 | 1/30/2018 | 1/30/2018 | A | PART |
Jim Storey
|
|
|
Fire Caulking - Lee ###-#### pending listing for 21/2 wall/ceilling fire stop for spk.
|
BLD-Other | 1/29/2018 | 1/29/2018 | 1/30/2018 | P | NR |
Jim Storey
|
|
|
Fire Caulking - Lee ###-####
|
BLD-Other | 1/29/2018 | 1/29/2018 | 1/29/2018 | A | NR |
Jim Storey
|
|
|
Fire Caulking - Lee ###-####
|
FIRE-Final Inspection | 1/26/2018 | 1/29/2018 | 1/29/2018 | A | CANC |
Jim Page
|
|
|
Wrong inspector requested, this request is cancelled. Fire colking // Lee Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 1/24/2018 | 1/25/2018 | 1/26/2018 | A | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### Framing: 104/105/106/204/205/206/300/302/303/304/305/306/402/403/405/406
Drop ceiling fire caulking: 123/124/125/126//128.
|
BLD-Framing/Rough-in | 1/23/2018 | 1/24/2018 | 1/24/2018 | A | DEFR |
Jim Storey
|
|
|
Lee Scott Phone #: ###-####
|
BLD-Other | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | PASS |
Brandon Shaw
|
|
|
Fire caulking-
|
BLD-Energy code compliance | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PART |
Brandon Shaw
|
|
|
Units- 100 & 200
|
BLD-Framing/Rough-in | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PART |
Brandon Shaw
|
|
|
Units- 102, 103, 202, & 203
|
BLD-Framing/Rough-in | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### area 2 1st and 2nd as noted ok single units
|
BLD-Other | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | CANC |
Jim Storey
|
|
|
Lee-fire caulking in area 3 4th floor Phone #: ###-#### room drops ok insulation ceilling assembly 132 ok to cover
|
BLD-Framing/Rough-in | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-####132/232/332/432/101/201/301/401
|
BLD-Framing/Rough-in | 1/3/2018 | 1/4/2018 | 1/4/2018 | P | PART |
Jim Storey
|
|
|
Area 1 - Lee Phone #: ###-#### c/n
|
BLD-Energy code compliance | 12/29/2017 | 1/2/2018 | 1/2/2018 | A | PART |
Dave Hannah
|
|
|
Lee Phone #: ###-#### ceiling insulation pull down rooms 125.130.225,230,325,330 and truss repair rm 420 ok
|
BLD-Other | 12/28/2017 | 12/29/2017 | 12/29/2017 | A | PART |
Dave Hannah
|
|
|
Lee-fire caulking Phone #: ###-#### area 3 3rd floor rooms 308 318 drop ceilings ok to cover.
|
BLD-Other | 12/28/2017 | 12/28/2017 | 12/28/2017 | P | NH |
Tony Young
|
|
|
Lee-fire caulking Phone #: ###-####,,phoned.. no answer,, not on site,, others I talked to did not know anything
|
BLD-Energy code compliance | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### 320 322 ok
|
BLD-Framing/Rough-in | 12/19/2017 | 12/19/2017 | 12/19/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### 125/225/325/130/230/330/ ok
|
BLD-Energy code compliance | 12/14/2017 | 12/14/2017 | 12/15/2017 | P | DEFR |
Jim Storey
|
|
|
Lee Phone #: ###-#### out of time
|
BLD-Energy code compliance | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Jim Storey
|
|
|
lee 328/326/324/323/128/126/124/123
|
BLD-Framing/Rough-in | 12/11/2017 | 12/11/2017 | 12/11/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### 320/420/423/322/324/326/328/323 mech rms 3 and 4 th ok
|
BLD-Energy code compliance | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-####corridors ok all//124,126,128,123,224,226,228 223 framing ok//insulation ok 120/122,220,222
|
BLD-Framing/Rough-in | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### area 1 corridors ok all//124,126,128,123,224,226,228 223 framing ok//insulation ok 120/122,220,222
|
BLD-Framing/Rough-in | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Mike Jordan
|
|
|
Lee Phone #: ###-####. Framing inspection for rooms 124, 126, 123 128, 224,226, 223, 228 and mech rmson 1st. and 2nd. floors in area #2. Needs to provide rated washer boxes and provide Documentation on dryer boxes, patch and fire caulk all pre rock at furred walls. Still needs to provide UL documentation for plastic pipe through penetrations at 3hr. horizontal assembly. Engineer to review removal of OSB at shear wall. Remove low voltage boxes in fire partitions and provide rated box. Ok to insualte exterior walls and ceilings.
|
BLD-Framing/Rough-in | 11/30/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### ceillings rooms area 3 ok
|
BLD-Wall Bracing | 11/30/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### area 1 ok
|
BLD-Framing/Rough-in | 11/27/2017 | 11/28/2017 | 11/28/2017 | A | PASS |
Jim Storey
|
|
|
Area 2 - Lee Phone #: ###-#### area 1 120/220/121/221 stair 2 framing ok
|
BLD-Other | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
Jim Storey
|
|
|
roof nailing- lee Phone #: ###-####
|
BLD-Other | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Jim Storey
|
|
|
Fire Caulking- Lee Phone #: ###-#### area 3 1st floor ceilling fire stopping ok to cover drop ceillings
|
BLD-Energy code compliance | 11/16/2017 | 11/16/2017 | 11/17/2017 | P | PART |
Jim Storey
|
|
|
Lee Phone #: ###-#### insulation ok 3 hr collors w/pastic pipe require support bothsides of assembly
|
BLD-Energy code compliance | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | NR |
Jim Storey
|
|
|
roof nailing and framing// Lee Phone #: ###-####
|
BLD-Framing/Rough-in | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PART |
Jim Storey
|
|
|
roof nailing and framing// Lee Phone #: ###-#### grout/screws/nailling/ exterior 2 hr membrane needed
|
BLD-Framing/Rough-in | 11/8/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### 4th floor area 3 insulation ok//area 3 framing ok to stair 2#
|
BLD-Energy code compliance | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### insulation and rc ok 3rd floor area 3
|
BLD-Wall Bracing | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-####area 2 4th floor ok//area 2 3 rd floor ok
|
BLD-Framing/Rough-in | 11/1/2017 | 11/2/2017 | 11/2/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-####r/c and insulation 312/309/310/307/308 area 3 3rd floor//sheer walls ok 1st ans 2nd area 2 // roof nailling ok area 2.
|
BLD-Wall Bracing | 10/31/2017 | 11/1/2017 | 11/1/2017 | P | DEFR |
Jim Storey
|
|
|
Lee Phone #: ###-#### out of time
|
BLD-Framing/Rough-in | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-####area 3 4 th floor framing ok// area 3 2 nd floor insulation and rc channel ok to cover.
|
BLD-Other | 10/26/2017 | 10/26/2017 | 10/26/2017 | P | PART |
Jim Storey
|
|
|
Lee-RC channel area 3-2nd floor Phone #: ###-#### single rm west end of area
|
BLD-Framing/Rough-in | 10/24/2017 | 10/25/2017 | 10/25/2017 | P | PASS |
Jim Storey
|
|
|
Lee Scott Phone #: ###-#### corridors 1 and 2 floors area 2// 3dr floor area 3 ok to insulate.
|
BLD-Energy code compliance | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | PASS |
Jim Storey
|
|
|
Area 3, 1st floor - Lee Phone #: ###-#### insulation and rc ok to cover
|
BLD-Other | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | PASS |
Jim Storey
|
|
|
Roof nailing // Lee Scott Phone #: ###-####
|
BLD-Energy code compliance | 10/18/2017 | 10/18/2017 | 10/18/2017 | P | NR |
Jim Storey
|
|
|
Lee scott Phone #: ###-####
|
BLD-Framing/Rough-in | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### area 3 level 1 &2 ok to insulate/ firestopping and framing ok
|
BLD-Framing/Rough-in | 10/13/2017 | 10/16/2017 | 10/16/2017 | P | CANC |
Jim Storey
|
|
|
Adam-level 1 & 2 area 3 only Phone #: ###-####
|
BLD-Framing/Rough-in | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Jim Storey
|
|
|
framing for roof // Evan Phone #: ###-#### a#2 roof ok to cover// sheer wall 4 floor east side stair #2 ok to cover
|
BLD-Wall Bracing | 10/10/2017 | 10/10/2017 | 10/10/2017 | P | PASS |
Jim Storey
|
|
|
Lee-dry wall -1st floor area 3 Phone #: ###-####1 and 2 nd lid ok
|
BLD-Wall Bracing | 9/29/2017 | 10/2/2017 | 10/2/2017 | A | PASS |
Jim Storey
|
|
|
3rd floor, area 3 - lee Phone #: ###-#### ok for nailling
|
BLD-Other | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | PART |
Dave Hannah
|
|
|
fire wall insp// Lee Scott Phone #: ###-#### 4th floor stair tower 2 ok to move in shear wall
|
BLD-Other | 9/14/2017 | 9/15/2017 | 9/15/2017 | P | PASS |
Jim Storey
|
|
|
fire wall // early after noon or late morning // Lee Scott Phone #: ###-#### #2 4th floor east side stair gyp ok / 2nd floor exterior west end straps in place ok to cover no exterior fire protection required.
|
BLD-Wall Bracing | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | PASS |
Jim Storey
|
|
|
Lee-dry wall-shear nailing Phone #: ###-####shaft 4th floor area 3 ok/stair well area 3/3 ok corridor lid ok to cover 3/3floor
|
BLD-Wall cover | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PART |
Brandon Shaw
|
|
|
BLD 3, phase 2, area 2, 2nd floor stair well-shear. Same location, across hallway-mech chase, fire walls BLD 3, 2nd floor corridoor, 1hr ceiling cover OK
|
BLD-Wall Bracing | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PART |
Brandon Shaw
|
|
|
BLD 3, phase 2, stair well 2, 2nd floor shear anfd fire wall. OK to continue
|
BLD-Wall Bracing | 8/30/2017 | 8/31/2017 | 8/31/2017 | P | PART |
Brandon Shaw
|
|
|
Roof nailing and 2nd floor interior shear panels, Building 3
|
BLD-Framing/Rough-in | 8/24/2017 | 8/24/2017 | 8/24/2017 | P | PASS |
Jim Storey
|
|
|
2nd floor // Lee Phone #: ###-#### corridor framing of ceilling ok to pre rock south wing
|
BLD-Wall cover | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-#### pre rock 1st floor corridor 1/2 west to east south side ok
|
BLD-Wall Bracing | 8/9/2017 | 8/10/2017 | 8/10/2017 | A | PASS |
Jim Storey
|
|
|
Area 3, 4th floor - Lee Phone #: ###-#### exterior sheer ok
|
BLD-Other | 8/9/2017 | 8/9/2017 | 8/9/2017 | P | PASS |
Jim Storey
|
|
|
Lee-2 hour firewall Phone #: ###-####east stair first floor
|
BLD-Wall Bracing | 8/1/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-####1st floor area b interior sheer ok
|
BLD-Wall cover | 7/31/2017 | 7/31/2017 | 7/31/2017 | P | PASS |
Jim Storey
|
|
|
2nd layer west side stair 2 hr ok
|
BLD-Wall cover | 7/27/2017 | 7/28/2017 | 7/28/2017 | A | PASS |
Jim Storey
|
|
|
Reed Phone #: ###-#### west 1st layer stair 2 ok
|
BLD-Wall cover | 7/26/2017 | 7/27/2017 | 7/27/2017 | P | DEFR |
Jim Storey
|
|
|
Reed Phone #: ###-#### out of time
|
BLD-Wall Bracing | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Jim Storey
|
|
|
Lee Phone #: ###-####stair #2 sheer ok east and west
|
BLD-Footing | 7/11/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-#### deck placement #3 ok pending si/ fire collors ok for 3 hr/
|
BLD-Wall Bracing | 7/5/2017 | 7/6/2017 | 7/6/2017 | A | PASS |
Jim Storey
|
|
|
Reese Phone #: ###-#### south side center 1 st floor wood ext. sheer ok
|
BLD-Conference | 6/27/2017 | 6/28/2017 | 6/28/2017 | P | PART |
Jim Storey
|
|
|
Lee Phone #: ###-#### 2nd pt placment fire protection not called for insp.
|
BLD-Conference | 5/25/2017 | 6/6/2017 | 6/6/2017 | P | DONE |
Jim Storey
|
|
|
Evan Phone #: ###-####
|
BLD-Foundation | 5/25/2017 | 5/26/2017 | 5/26/2017 | P | PART |
Jim Storey
|
|
|
Evan-pre-rebar for podium deck Phone #: ###-#### si on site for bar and pt// fire collors in place for 3 hr protection.
|
BLD-Foundation | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PART |
Jim Storey
|
|
|
Wall // Evan Phone #: ###-#### pending si reports
|
BLD-Foundation | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PART |
Jim Storey
|
|
|
Evan-partial-pour time 1:00 Phone #: ###-#### placed w/si
|
BLD-Other | 4/27/2017 | 4/28/2017 | 4/28/2017 | P | PEND |
Dave Hannah
|
|
|
concrete wall insp// Evan Phone #: ###-#### ok after spec inspection sign off
|
BLD-Wall Bracing | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | PART |
Jim Storey
|
|
|
Evan Phone #: ###-#### pending si
|
BLD-Other | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | PART |
Jim Storey
|
|
|
columns // Evan Phone #: ###-#### placed w si pending report
|
BLD-Conference | 4/17/2017 | 4/20/2017 | 4/20/2017 | A | DONE |
Jim Storey
|
|
|
Evan-wants it at 10:00 Phone #: ###-####
|
BLD-Footing | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | PART |
Jim Storey
|
|
|
Evan Phone #: ###-#### ft placed w/si pending reports
|
BLD-Footing | 4/17/2017 | 4/18/2017 | 4/18/2017 | A | PASS |
Jim Storey
|
|
|
Evan-columns-pour time 10:15 Phone #: ###-#### bar exposer ok
|
BLD-Footing | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | PART |
Jim Storey
|
|
|
Evan Phone #: ###-#### si east end
|
BLD-Footing | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PART |
Jim Storey
|
|
|
Evan Phone #: ###-#### placed with si pending reports
|
BLD-Foundation | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PART |
Jim Storey
|
|
|
rebar // EVAN Phone #: ###-#### ft phase 3 si on site
|