Permit Information
Permit NumberBLD17-00363
StatusIssued
Name APEX BUILD & REMODEL LLC
Site Address 4111 S BROADWAY AVE
Project NameRed Lion - Remodel
Customer Number 
ePlanReviewYes
Description
(RED LION INN & SUITES – HOTEL ROOMS AND FOOD PREPARATION AREA REMODEL – FORMERLY SHILO INN) (CZC17-00051) (12-1-17 PLAN MODIFICATION TO CHANGE THE SCOPE OF WORK.) The fire sprinkler system is used for building area increase, for story increase, and for occupancy. To remodel 3 hotel rooms located on the 23,077 square foot upper grade level story (2nd story) of an existing 74,435 square foot hotel building to be accessible to the disabled in compliance with current accessibility standards. On that same story, an existing meeting room will be converted to a breakfast dining room, an existing hotel room will be converted to a food preparation area, an existing hotel room will be converted to an office, and two existing restrooms within the existing exercise room will be upgraded to be accessible to the disabled. All existing bearing walls and shear walls will be maintained. The restrooms in every hotel room (124 total) will also be remodeled. Work includes new bathtubs, exhaust fans, and ceiling radiation dampers. Existing 1-hr corridors on all stories are required to be maintained. A new PTAC unit will be installed to serve each hotel room. New PTAC units will also be installed to serve the new food preparation area, the new office, the existing exercise room, the hotel lobby, the existing dwelling unit, and the breakfast dining room. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference5/15/20205/18/20205/18/2020APART
DetailsJim Storey
Status?//Rough-in 5/9/2020 5/11/2020 5/11/2020 A PART





DetailsJack Reynolds

1st phase new part two last units on main floor and 12 units on the 3rd floor(floor above) Phone #: ###-#### Inspection requested via web by yuriy kryachun
- units 240,241 exhaust duct R/I ok
- unit 330- 341 exhaust duct R/I ok
- ok for first layer sheetrock and fire caulk
BLD-Framing/Rough-in4/12/20184/13/20184/13/2018APASS
DetailsJim Storey
Roman Phone #: 208-###-#### first floor rooms and lobby ok to cover
BLD-Other3/14/20183/14/20183/14/2018PPASS
DetailsJim Storey
Roman-wants and ok to cover pantry meeting room Phone #: ###-####
BLD-Other2/23/20182/26/20182/26/2018APASS
DetailsJim Storey
Fire rating exhaust shaft - Roman Phone #: ###-#### 4th floor west building ok
BLD-Conference1/29/20181/29/20181/29/2018PPEND
DetailsBob Archibald
Conference on mechanical bath fan requirements in both old and new construction areas. Old or original building bath areas require 5/8 sheetrock above fan and minimum 26 gage duct to center wall. New building bath areas require removal of fan units in shaft and relocation into a drop down soffit and 26 gage duct from fan to shaft. Both areas shall have fire dampered fans.
BLD-Other1/18/20181/19/20181/19/2018APEND
DetailsDave Hannah
Roman-fire wall-from shower to hallway-when you get there ask for Sergy to show you where inspection is needed Phone #: ###-#### looked at concrete board on shower wall looks ok but need to see paper work for listing
BLD-Framing/Rough-in12/13/201712/14/201712/14/2017APASS
DetailsJim Storey
Romeo ###-#### Spoke with Bob and he said framing in the rooms, not bathrooms, is ok. wall pach and wall finshes ok/doors to be replaced thu rout building. corridor wall and shaft on hold until feb.
BLD-Conference12/7/201712/7/201712/7/2017PPEND
DetailsJim Storey
SWO issued. No cover of exposed framing without inspector approval ( walls, floor/ceilings and shafts). Rated/labeled door and frame assemblies required in corridoor on west 1/2 of building past 2hr rated wall corridoor. Architect also reviewed site and existing conditions at SWO issuance. Majority of violations were observed on 4th floor as 2nd and 3rd floors are occupied. Verification of corridoor wall construction on 2nd and 3rd floor at showers will be required.
BLD-Conference12/6/201712/6/201712/6/2017PPEND
DetailsJim Storey
Site review with plum/mec and electrical supervisors. Mec has issued a SWO on mechanical fan installations. Cooridors and fire rated construction of walls, floor/ceilings and shafts have been compromised. Will recommend to BO that no occupancy should be allowed untill fire rated provisions have been corrected.