BLD-Final | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Sly
|
|
|
Requesting Mike Jordan. 12pm time frame would be great if possible, but if not, I can be flexible with an hour notice. Please call to confirm. Thank you. Phone #: ###-#### Inspection requested via web by Cameron Craven
|
DOC - Permit Finaled | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 9/25/2018 | 9/27/2018 | 9/27/2018 | P | DONE |
Mike Jordan
|
|
|
Getting close to finished and want to be on the same page with Boise as to expectations for final. Request a visit by Mike Jordan to discuss requirements. Please call first and would appreciate an hour of notice. Thanks. Phone #: ###-#### Inspection requested via web by Cameron Craven
|
BLD-Framing/Rough-in | 6/7/2018 | 6/8/2018 | 6/8/2018 | P | PART |
Mike Jordan
|
|
|
Requesting Mike Jordan. He has been onsite previously. Double checked and nailed off sheeting. Installed blocking in corners. Installed purlins. Want gable bracing verified before nailing in. Phone #: ###-#### Inspection requested via web by Cameron Craven. All issues have been resolved. ok to cover after electrical rough in inspection.
|
BLD-Framing/Rough-in | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PART |
Mike Jordan
|
|
|
Cameron Phone #: ###-####. Install additional blocking at corners, nail sheathing at all missed areas. Brace gable ends and install purlins on botom chords of trusses.
|
BLD-Foundation | 3/21/2018 | 3/21/2018 | 3/21/2018 | P | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####
|
BLD-Footing | 3/19/2018 | 3/20/2018 | 3/20/2018 | A | PASS |
Mike Jordan
|
|
|
jose Phone #: ###-####
|