BLD-Final | 11/29/2017 | 11/30/2017 | 11/30/2017 | P | PASS |
Mike Jordan
|
|
|
Garage door code is 2468
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 11/30/2017 | 11/30/2017 | 11/30/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Joel Hirtle
|
BLD-Energy code compliance | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Joel Hirtle
|
BLD-Energy code compliance | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PEND |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Energy ok, pending framing corrections.
|
BLD-Framing/Rough-in | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | FAIL |
Mike Jordan
|
|
|
Re-frame inspection Inspection requested via web by Joel Hirtle. All framing corrections not made, still needs to install the A35's on gable end and add the additional stud and squash blocks to B3 truss.
|
BLD-Framing/Rough-in | 10/11/2017 | 10/11/2017 | 10/11/2017 | P | CANC |
Mike Jordan
|
|
|
Please schedule for later PM Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Energy code compliance | 10/11/2017 | 10/11/2017 | 10/11/2017 | P | NR |
Mike Jordan
|
|
|
Please schedule for later PM Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Other | 10/10/2017 | 10/11/2017 | 10/11/2017 | A | CANC |
Mike Jordan
|
|
|
Mechanical inspection please. Phone #: ###-#### Inspection requested via web by Joel Hirtle. wrong inspection.
|
BLD-Energy code compliance | 10/9/2017 | 10/10/2017 | 10/10/2017 | P | CANC |
Mike Jordan
|
|
|
Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 10/9/2017 | 10/10/2017 | 10/10/2017 | P | FAIL |
Mike Jordan
|
|
|
Inspection requested via web by Joel Hirtle. Complete lateral bracing on C4, C4A and C5 trusses. Repair cut dtuds in portal frame. Install the A35's on gable end trusses as noted on engineering. Provide additional stud for B3 2ply at west wall and squash block below. Ok to insulate AFTER mech. rough in inspection has passed. Correction notice issued.
|
BLD-Wall Bracing | 9/28/2017 | 9/28/2017 | 9/29/2017 | P | PART |
Brandon Shaw
|
|
|
Exterior only
|
BLD-Foundation | 8/11/2017 | 8/14/2017 | 8/15/2017 | P | PASS |
Brandon Shaw
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 8/10/2017 | 8/11/2017 | 8/11/2017 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Grading Inspection | 8/9/2017 | 8/9/2017 | 8/9/2017 | A | PASS |
Mike Jordan
|
|
|
Need to have preliminary sight inspection prior to dig. ESC card posted Phone #: ###-#### Inspection requested via web by Joel Hirtle
|