BLD-Final | 7/12/2019 | 7/12/2019 | 7/12/2019 | P | PASS |
Dave Hannah
|
|
|
Request permit to be closed. Last note indicated that fire protection was needed in 2nd floor tenant office. Delta Fire pulled a permit and installed missing sprinkler coverage that has been signed off by the fire inspector. Thanks! Phone #: ###-#### Inspection requested via web by Brandon McCurdy
|
BLD-Final | 12/26/2018 | 12/27/2018 | 12/28/2018 | A | NR |
Dave Hannah
|
|
|
We were awaiting a final on electrical. Electrical Contractor went out of business. A new piggy back electrical permit was pulled to address the previous correction notice. The work is done, electrical is now signed off. Therefore, we request the building permit be signed off (final). Phone #: ###-#### Inspection requested via web by Brandon McCurdy. Needs fire sprinckler work and sign offs
|
BLD-Framing/Rough-in | 11/29/2017 | 11/29/2017 | 11/30/2017 | P | PART |
Dave Hannah
|
|
|
I will be picking up the current permit set dated 11/28/17 by 10:00 am. If we could do the framing inspection later morning to be sure I have the current permit set onsite that would be great. Thanks. Phone #: ###-#### Inspection requested via web by Brandon McCurdy basement food prep area A ok to cover
|
BLD-Framing/Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | CANC |
Dave Hannah
|
|
|
I will be picking up the current permit set dated 11/28/17 by 10:00 am. If we could do the framing inspection later morning to be sure I have the current permit set onsite that would be great. Thanks. Phone #: ###-#### Inspection requested via web by Brandon McCurdy
|