BLD-Framing/Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Mike Jordan
|
|
|
Clint Phone #: ###-####
|
BLD-Wall Bracing | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PASS |
Mike Jordan
|
|
|
Shear // Jay Phone #: ###-####. Exterior shear nailing only ok.
|
BLD-Wall Bracing | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | CANC |
Mike Jordan
|
|
|
Jay Phone #: ###-####
|
BLD-Wall Bracing | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | FAIL |
Jim Sly
|
|
|
out of time (storey) Called Contr......Not Per Engineering. Shear nailing not correct. Anchor bolts.....Engeneer to approve or provide fix.
|
BLD-Wall Bracing | 8/17/2017 | 8/17/2017 | 8/17/2017 | P | DEFR |
Jim Storey
|
|
|
Jay Phone #: ###-#### out of time
|
BLD-Framing/Rough-in | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | FAIL |
Mike Jordan
|
|
|
Jesus needs a sheating inspection Phone #: ###-####. No city approved plans on site. No inspection. Correction notice posted.
|
BLD-Foundation | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | PART |
Mike Jordan
|
|
|
Zack Phone #: ###-####
|
BLD-Foundation | 7/25/2017 | 7/26/2017 | 7/26/2017 | P | PART |
Dave Hannah
|
|
|
request for 3pm // Zach Phone #: ###-#### thi was a ftg inspection setbacks looked ok depth ok rebar in but needed to be chaired
|