BLD-Aging Inspection | 7/31/2018 | 7/31/2018 | 8/1/2018 | | PEND |
Mike Jordan
|
|
|
|
BLD-Final | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp occ. Will be ok for perm occ once zoing signs perm. No card on site to sign.
|
FIRE-Final Inspection | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | FAIL |
Troy Cobbley
|
|
|
Missing ceiling in unit 102 closet.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Final | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | NR |
Mike Jordan
|
|
|
Mechanical and Fire Life Safety scheduled for PM as well. Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | FAIL |
Troy Cobbley
|
|
|
Missing fire extinguishers, missing ceilings, inspection stopped
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 5/16/2018 | 5/16/2018 | 5/16/2018 | P | FAIL |
Jim Page
|
|
|
FIR permits for fire sprinkler and fire alarm need to be finaled before life fire safety inspection can be performed.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Energy code compliance | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | PASS |
Dave Hannah
|
|
|
Please accommodate a 4 o''clock inspection. Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | PART |
Brandon Shaw
|
|
|
Pending Fire Sprinkler inspection
|
BLD-Wall Bracing | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | DEFR |
Mike Jordan
|
|
|
Interior footings, Concrete is scheduled for 8am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Foundation | 12/17/2017 | 12/18/2017 | 12/18/2017 | A | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 12pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 12/8/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
Frost protection required
|