BLD-Final | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | PASS |
Jim Sly
|
|
|
Thanks Tony, Phone #: ###-#### Inspection requested via web by Tony Inserra OK for Perm Occ.
|
BLD-Final | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PART |
Jim Sly
|
|
|
I have a planning ; zoning scheduled for a pm inspection also. Sorry for the confusion yesterday. Thanks Tony, Phone #: ###-#### Inspection requested via web by Tony Inserra OK for Temp Occ. OK for Perm Occ when Plumb. Perms.
|
FIRE-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
Tony Phone #: ###-####
|
BLD-Final | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | NR |
Jim Sly
|
|
|
Tony Phone #: ###-#### Need Zoning final.
|
BLD-Other | 7/23/2018 | 7/24/2018 | 7/24/2018 | P | CANC |
Jim Sly
|
|
|
Landscaping // Tony Phone #: ###-####
|
BLD-Foundation | 5/15/2018 | 5/16/2018 | 5/16/2018 | P | PART |
Jim Sly
|
|
|
cmu... pour at 1 // Tony Phone #: ###-#### MTI on site.....
|
BLD-Concrete | 5/14/2018 | 5/15/2018 | 5/16/2018 | P | PART |
Jim Sly
|
|
|
rebar-masonary- Tony Phone #: ###-#### CMU....OK pending MTI special inspection, tests and approvals.
|
BLD-Other | 5/10/2018 | 5/14/2018 | 5/14/2018 | A | PART |
Jim Storey
|
|
|
Tony---Masonary Inspection CMU Block-rebar, 11am grout MPI will be there Phone #: ###-#### si placement
|
BLD-Other | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Jim Sly
|
|
|
Tony---Masonery-Grout at 12:30 Phone #: ###-#### MTI on site.
|
BLD-Other | 5/9/2018 | 5/10/2018 | 5/10/2018 | P | PART |
Jim Sly
|
|
|
grout insp (grout at 3pm) (MTI will be out on site) // Tony Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 4/30/2018 | 5/1/2018 | 5/1/2018 | P | PART |
Jim Sly
|
|
|
Late afternoon, around 2:30 or 3 - Tony Phone #: ###-#### OK pending MTI special insp, tests and approvals.
|