BLD-Final | 3/17/2020 | 3/17/2020 | 3/19/2020 | P | PART |
Dave Hannah
|
|
|
Tim - Inspection for Temporary Occ Phone #: ###-#### ok for tco
|
FIRE-Final Inspection | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete, signature card not available at time of inspection.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | FAIL |
Jim Page
|
|
|
Fire riser room is not a rated room as required by Boise Municipal Code, Chapter 7 Fire Prevention Code section 903.1.2. Provide building permit fire review comments for project, documents are required to be onsite, per conversation with point of contact they are not onsite. Install addressing that is compliant with 2016 IFC section 505, current addressing does not meet the requirements of section 505. Provide corner lot addressing as defined in the BMC Chapter 7 section 505.3. Provide fire extinguishers with current inspection tags for each unit, fire extingiushers can be mounted under the sink. Correct the addressing with the monitoring company.
Tim Phone #: ###-####
|
BLD-Conference | 1/6/2020 | 1/6/2020 | 1/7/2020 | P | DONE |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Energy code compliance | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Dave Hannah
|
|
|
Units 106, 107, 108 - Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 11/4/2019 | 11/5/2019 | 11/5/2019 | P | PASS |
Dave Hannah
|
|
|
Unit 106 - Curt Phone #: ###-####
|
BLD-Energy code compliance | 11/4/2019 | 11/5/2019 | 11/5/2019 | A | PASS |
Dave Hannah
|
|
|
Unit 109 and 110 - Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 11/1/2019 | 11/4/2019 | 11/4/2019 | P | PASS |
Dave Hannah
|
|
|
units 106 & 107 // Kurt Phone #: ###-#### unit 107 only
|
BLD-Framing/Rough-in | 10/24/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Dave Hannah
|
|
|
unit 108 only // Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | PASS |
Mike Jordan
|
|
|
Kirt Phone #: ###-####. Unit 109 only.
|
BLD-Framing/Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending PLM rough-in approval...
|
BLD-Foundation | 4/25/2019 | 4/25/2019 | 4/26/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####third floor center walls ok
|
BLD-Foundation | 4/15/2019 | 4/15/2019 | 4/16/2019 | P | PART |
Dave Hannah
|
|
|
Tim Phone #: ###-#### third floor ext walls ok
|
BLD-Foundation | 2/11/2019 | 2/11/2019 | 2/12/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-#### second level and ext stair north bld and south stair
|
BLD-Footing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PASS |
Dave Hannah
|
|
|
wall-tim Phone #: ###-#### first floor center walls
|
BLD-Footing | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | PART |
Dave Hannah
|
|
|
wall // tim Phone #: ###-#### first level north building
|
BLD-Foundation | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | NR |
Mike Jordan
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PART |
Dave Hannah
|
|
|
pouring at 3:30 Tim Phone #: ###-#### walls between units ok
|
BLD-Foundation | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PART |
Dave Hannah
|
|
|
Tim-pour time 3:00 Phone #: ###-#### first 4 ft ok
|
BLD-Footing | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Dave Hannah
|
|
|
Pour at 3 // Tim Phone #: ###-####
|