Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD17-03243
StatusFinaled
Name STUDIO F3 PLLC
Site Address 2417 W BANK DR
Project NameGem State Securities Building
Customer Number 
ePlanReviewYes
Description
(GEM STATE SECURITIES BUILDING) Permit is to remodel the second and third floor within an existing 24,000 sq. ft. building. There is an update agreement to install fire sprinklers throughout the building and to have a code compliant rated stair enclosure. Approval is contingent upon adhering to the approved plans on file. Work includes: on the 2nd/3rd floors construction of select interior nonbearing walls to create offices, select new door/door frames, select new light fixtures, stair enclosure work to make enclosure 1-hour rated, electrical work, Plumbing work and interior finishes in compliance with Ch. 8 of the 2012 IBC. This building will be fully Fire Sprinklered with the upgrade agreement and shall be installed by 1/1/2018. Occupancy of the third and second floor is contingent on final approval of the building permit and receipt of a signed "Upgrade Agreement" between the building owner and Boise City Building Official & Fire Marshall. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection7/11/20187/11/20187/11/2018 DONE
DetailsJim Storey
agreement on file
DOC - Permit Finaled7/11/20187/11/20187/11/2018PPASS
DetailsJim Storey
BLD-Final5/7/20185/7/20185/7/2018PPASS
DetailsJim Storey
FIRE-Final Inspection5/7/20185/7/20185/7/2018PPASS
DetailsJim Page
Shunt trip for elevator and door release under active fire alarm complete. Final life fire safety inspection for area of work complete.
BLD-Final2/9/20182/12/20182/12/2018APART
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Justin Schwartz temp occ ok/ pending fire temp/ need fire stop listing
BLD-Final2/9/20182/9/20182/9/2018PPART
DetailsJim Storey
temp occ ok/ pending fire temp/ need fire stop listing
FIRE-Final Inspection2/9/20182/9/20182/9/2018PPART
DetailsJim Page
Fire sprinkler inspection complete for scope of work areas, fire alarm inspection partially complete, contractor is waiting for parts to shunt trip elevator, fire extinguishers are in place with current inspection tags in scope of work areas. Partial completion for life fire safety for TCO, elevator shunt will be tested when install is complete.
FIRE-Conference1/18/20181/19/20181/19/2018ADONE
DetailsJim Page
Fire conference complete.
BLD-Final1/8/20181/8/20181/8/2018PNR
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Justin Schwartz pending agreement with buildinf offical fire cheif to define scope of occupance.
BLD-Final1/1/20181/2/20181/2/2018PNR
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Justin Schwartz
BLD-Framing/Rough-in12/4/201712/5/201712/5/2017PPART
DetailsJim Storey
Inspection requested via web by Justin Schwartz gyp ok pending pic for isue.
BLD-Framing/Rough-in11/20/201711/21/201711/21/2017PPASS
DetailsJim Storey
Inspection requested via web by Justin Schwartz 2 and 3 rd walls ok to cover