BLD-Final | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer
|
DOC - Permit Finaled | 6/20/2018 | 6/20/2018 | 6/20/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 2/7/2018 | 2/8/2018 | 2/8/2018 | P | PASS |
Tony Young
|
|
|
Basement - add (2) 2x8 header and floor beams bearing Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Energy code compliance | 2/8/2018 | 2/8/2018 | 2/8/2018 | P | PASS |
Tony Young
|
|
|
Basement - add (2) 2x8 header and floor beams bearing Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Wall cover | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Brandon Shaw
|
|
|
OK to cover walls exept interior basement bedroom walls... Provide revised/approved for as built- (2) 2x8 header and floorbeams not having full bearing
|
BLD-Framing/Rough-in | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Footing | 11/6/2017 | 11/7/2017 | 11/7/2017 | A | PASS |
Jim Storey
|
|
|
(2) Interior footing inspections in existing basement floor. Refer inspection around 10am, if possible. Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Foundation | 10/30/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Dave Hannah
|
|
|
Rebar for Basement walls Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Footing | 10/17/2017 | 10/19/2017 | 10/19/2017 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer,, basement footing ok,, work in progress
|