BLD-Final | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Mike Jordan
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
|
DOC - Permit Finaled | 9/28/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | NR |
Mike Jordan
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman. Needs public works final and final letter from special inspection agency.
|
FIRE-Final Inspection | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PART |
Troy Cobbley
|
|
|
Temp for life safety until the project related Grading Permit is finaled
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
|
BLD-Final | 8/26/2018 | 8/27/2018 | 8/27/2018 | A | CANC |
Mike Jordan
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
|
FIRE-Final Inspection | 8/26/2018 | 8/27/2018 | 8/27/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need fire extinguishers and Grading Permit inspection.
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
|
BLD-Foundation | 12/29/2017 | 12/29/2017 | 12/29/2017 | P | PART |
Brandon Shaw
|
|
|
Work in progress, ok pending special inspection.
|
BLD-Footing | 12/22/2017 | 12/22/2017 | 12/22/2017 | P | PART |
Mike Jordan
|
|
|
pour around 1pm-James Phone #: ###-####. Work in progress, ok pending special inspection.
|