BLD-Final | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
DOC - Permit Finaled | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | DONE |
Tony Young
|
|
|
Ron Phone #: ###-####// 4.0
|
BLD-Final | 4/19/2019 | 4/22/2019 | 4/22/2019 | P | PEND |
Tony Young
|
|
|
Ron Phone #: ###-####,, needs hillside approval
|
BLD-Aging Inspection | 4/4/2019 | 4/4/2019 | 4/5/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/3/2019 | 4/3/2019 | 4/4/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 11/20/2018 | 11/21/2018 | 11/20/2018 | A | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
BLD-Framing/Rough-in | 11/14/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
BLD-Wall Bracing | 8/24/2018 | 8/24/2018 | 8/24/2018 | P | PASS |
Tony Young
|
|
|
Ron- Phone #: ###-####
|
BLD-Wall Bracing | 8/23/2018 | 8/23/2018 | 8/24/2018 | P | PART |
Tony Young
|
|
|
Ron-soffits and stairwells Phone #: ###-####,, soffits ok
|
BLD-Other | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PART |
Tony Young
|
|
|
Party wall - Aaron Phone #: ###-####,, 2nd floor over garage ok
|
BLD-Other | 7/3/2018 | 7/5/2018 | 7/5/2018 | A | PART |
Tony Young
|
|
|
fire wall // Ron Phone #: ###-####,, lower garage firewall ok
|
BLD-Other | 6/28/2018 | 6/28/2018 | 6/28/2018 | P | PART |
Tony Young
|
|
|
Aaron-party wall Phone #: ###-####,, upper main level firewall,, work in progress
|
BLD-Foundation | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Tony Young
|
|
|
wall-Austin Phone #: ###-####
|
BLD-Footing | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | DONE |
Tony Young
|
|
|
Austin Phone #: ###-####, upper house footings
|
BLD-Foundation | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Tony Young
|
|
|
Austin Phone #: ###-####,, back basement walls,, work in progress
|
BLD-Foundation | 4/24/2018 | 4/26/2018 | 4/26/2018 | A | NR |
Tony Young
|
|
|
Austin Phone #: ###-####
|
BLD-Foundation | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | PART |
Tony Young
|
|
|
Austin Phone #: ###-####,, rear footings
|
BLD-Foundation | 4/17/2018 | 4/17/2018 | 4/17/2018 | P | PART |
Brandon Shaw
|
|
|
Front and side stem walls, and back wall footing
|
BLD-Footing | 4/9/2018 | 4/10/2018 | 4/10/2018 | A | PART |
Brandon Shaw
|
|
|
Work in progress
Front and side wall footings, back wall footing to be poured at later date
|