BLD-Final | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Dave Hannah
|
|
|
Steve Phone #: ###-####
|
FIRE-Final Inspection | 5/17/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Jim Page
|
|
|
Previously noted items have been repaired. Fire sprinkler inspection complete, fire alarm inspection complete, fire exitnguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
Steve Phone #: ###-####
|
FIRE-Final Inspection | 5/14/2018 | 5/14/2018 | 5/14/2018 | P | FAIL |
Jim Page
|
|
|
Missing ceiling tile for fire sprinkler needs installed for heat collection. Sheetrock needs to be installed in remodeled restroom for fire sprinkler head heat collection.
Steve-please call 15 mintues prior for access Phone #: ###-####
|
FIRE-Final Inspection | 5/2/2018 | 5/2/2018 | 5/2/2018 | P | FAIL |
Jim Page
|
|
|
Tenants are in space conducting business, no fire sprinkler permit has been issued and fire sprinkler modifications are required for new tenant space, Ron Johnson with Boise Fire Department has been contacted and he supports my action, tenant business cannot be conducted until all inspections have been completed and passed, there has not been a C of O or TCO issued at this time.
|