BLD-Final | 2/20/2019 | 2/21/2019 | 2/21/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 2/21/2019 | 2/21/2019 | 2/21/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 2/20/2019 | 2/21/2019 | 2/21/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.92
|
BLD-Other | 12/19/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Brandon Shaw
|
|
|
Soffit inspection,
|
BLD-Energy code compliance | 12/17/2018 | 12/19/2018 | 12/20/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 11/21/2018 | 11/23/2018 | 11/23/2018 | A | PART |
Brandon Shaw
|
|
|
Per plans- Floor to floor straps to be installed before framing rough-in... Detail 3, pg S1.2- Shear transfer to be followed... Garage wall, edge blocking needed...
|
BLD-Foundation | 10/18/2018 | 10/18/2018 | 10/18/2018 | A | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|