BLD-Final | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PART |
Mike Jordan
|
|
|
Ok for temp occ. Final occ pending public works approval, zoning approval, fire/life safety giving perm occ. and completing the envelope for 1hr. construction in riser room, providing final letter from special inspection agency and posting the correct occupant load sign in gym.
|
FIRE-Final Inspection | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
The "trouble" issues with the fire alarm panel need resolved prior to a to a final for the life safety. Ron Phone #: ###-####
|
FIRE-Final Inspection | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given with Boise Fire approval until the project related fire alarm permit is finaled the exit discharge light is repaired and the fire hydrant issue is addressed.
Phone #: ###-####
|
FIRE-Final Inspection | 8/14/2019 | 8/14/2019 | 8/14/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled, need the fire hydrant addressed, need the west exit discharge light addressed. Ron Phone #: ###-####
|
FIRE-Final Inspection | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | FAIL |
Jim Page
|
|
|
Project related FIR permits need to inspected and finaled before life fire safety. Informed point of contact on 09AUG2019 that the fire hydrant on the southeast side of project is pointed the wrong way, steamer connection needs to be pointing at the fire lane, response was "I think that was the school disticts scope". Fire hydrants are on page A1.01 and are part of the new scope of work. Hydrant on the northwest side is in different location than what is shown on the city approved drawings. No other items inspected at this time.
Ron Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | NR |
Mike Jordan
|
|
|
Charlie Phone #: ###-####
|
BLD-Framing/Rough-in | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PART |
Brandon Shaw
|
|
|
Vestibule lid, between new building and existing...
|
BLD-Wall Bracing | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | PASS |
Mike Jordan
|
|
|
Charlie- nailing Phone #: ###-####. Box out of intercom box in 1hr. wall ok.
|
BLD-Framing/Rough-in | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Interior steel stud framed walls and hardlids for classrooms and restrooms ok to cover.
|
BLD-Framing/Rough-in | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Reamainder of anchor bolts on exterior shear walls.
|
BLD-Framing/Rough-in | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Interior steel stud framed walls for resrooms, storage rooms off of gym between grids 2 and 3.
|
BLD-Wall Bracing | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PASS |
Mike Jordan
|
|
|
Nailing inspection-Charlie Phone #: ###-####
|
BLD-Wall Bracing | 3/12/2019 | 3/13/2019 | 3/13/2019 | A | PASS |
Mike Jordan
|
|
|
Nailing inspection- Charlie Phone #: ###-####
|
BLD-Framing/Rough-in | 2/8/2019 | 2/11/2019 | 2/11/2019 | A | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Interior bearing wall on gridline 3 ok toone side.
|
BLD-Wall cover | 1/14/2019 | 1/14/2019 | 1/14/2019 | P | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Interior side of 1hr. wall ok.
|
BLD-Wall Bracing | 1/14/2019 | 1/14/2019 | 1/14/2019 | P | PART |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Exterior walls, work in progress.
|
BLD-Wall cover | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | PART |
Brandon Shaw
|
|
|
Fire wall, West side, seams mud and taped...
|
BLD-Wall Bracing | 1/8/2019 | 1/8/2019 | 1/8/2019 | P | PASS |
Mike Jordan
|
|
|
shear // Charlie Phone #: ###-####inner layer of 5/8 densae glass for shear and 1hour assembly ok.
|
BLD-Framing/Rough-in | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | PART |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Infill for existing window.
|
BLD-Foundation | 12/6/2018 | 12/6/2018 | 12/6/2018 | P | PART |
Brandon Shaw
|
|
|
Interior footings cleaned... Contractor is going to keep covered until Tues, 11Dec2018, 5 days...
|
BLD-Concrete | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PART |
Mike Jordan
|
|
|
slab on grad // Charlie Phone #: ###-####. Needs to clean bottom of interior thickend footings and provide dobees.
|
BLD-Foundation | 11/5/2018 | 11/6/2018 | 11/6/2018 | P | PART |
Mike Jordan
|
|
|
stem wall // Charlie Phone #: ###-####
|
BLD-Footing | 10/31/2018 | 11/1/2018 | 11/1/2018 | A | DEFR |
Mike Jordan
|
|
|
Charley Phone #: ###-####
|
BLD-Footing | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PART |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Work in progress on footing next to existing building on grids 4.9 and B.6.
|
BLD-Concrete | 10/15/2018 | 10/16/2018 | 10/16/2018 | P | PART |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Work in progress on installing reiforcement for thickend footing and interior slab on grade. Will have specail inspection.
|
BLD-Foundation | 9/18/2018 | 9/18/2018 | 9/18/2018 | P | PART |
Mike Jordan
|
|
|
steam wall // Charlie Phone #: ###-####. Work in progress. Will hve special inspection, perimeter stemwalls.
|
BLD-Footing | 9/6/2018 | 9/7/2018 | 9/7/2018 | P | PART |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Perimeter footings. Noted insufficient clearances from bottom rebar. Will have special inspection. Special inspector to verify correction. Placement will be on Monday Sept. 10th.
|