BLD-Final | 5/6/2019 | 5/7/2019 | 5/7/2019 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Kevin Phone #: ###-#### Inspection requested via web by Kevin Antonucci
|
BLD-Final | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | NR |
Jim Storey
|
|
|
Kevin Phone #: ###-#### Inspection requested via web by Kevin Antonucci Number FIR18-00930 Status Fee Preparation Name VIKING AUTOMATIC SPRINKLER CO
|
FIRE-Final Inspection | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need plans and small documents and the sprinkler permit finaled. Kevin Phone #: ###-####
|
BLD-Final | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | CANC |
Mike Jordan
|
|
|
Kevin Phone #: ###-####
|
BLD-Conference | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | PASS |
Jim Storey
|
|
|
insp record recored in wrong bld for tennent build out. all activities are ok for temp occ for bld18-01819. fire and bld. 301
|
BLD-Final | 2/23/2019 | 2/25/2019 | 2/25/2019 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Antonucci Phase 4 and Phase 5 complete. exit signage at double doors esat center/ check diangle 2/3 south pod exit sepyration.
|
FIRE-Final Inspection | 2/23/2019 | 2/25/2019 | 2/25/2019 | A | PART |
Jim Page
|
|
|
Life fire safety inspection for Phase 4 and Phase 5 complete for TCO
Phone #: ###-#### Inspection requested via web by Kevin Antonucci
|
BLD-Final | 1/17/2019 | 1/18/2019 | 1/18/2019 | P | PART |
Jim Storey
|
|
|
Call Kevin when you arrive. Phone #: ###-#### Inspection requested via web by Kevin Antonucci survery area ok to occupy.
|
FIRE-Final Inspection | 1/17/2019 | 1/18/2019 | 1/18/2019 | P | PART |
Troy Cobbley
|
|
|
life safety for Servery Area, Phase 3 is passed. Kevin is going to finish mounting the two fire extinguishers. Exit signs and emergency lights tested.
Call Kevin when you arrive. Phone #: ###-#### Inspection requested via web by Kevin Antonucci
|
BLD-Ceiling Grid Inspection | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Jim Storey
|
|
|
ceilling ok to flood/ tile change will need smoke and flame spread upon reinstal.
|
BLD-Wall cover | 12/28/2018 | 12/28/2018 | 12/28/2018 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Antonucci phase 3 ok
|
BLD-Framing/Rough-in | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Mike Jordan
|
|
|
Interior steel stud framed walls ok.
|
FIRE-Final Inspection | 11/21/2018 | 11/21/2018 | 11/21/2018 | P | PART |
Jim Page
|
|
|
Temporary audio visual notification for phase 2 on fire alarms is adequate for TCO, each phase will require fire alarm testing in the future. Fire sprinklers complete for phase 2, fire alarms are operation in phase 2 area, fire extinguishers for phase 2 are placed with current inspection tags. Final life fire safety inspection for phase 2 TCO complete.
|
FIRE-Final Inspection | 11/16/2018 | 11/19/2018 | 11/19/2018 | P | FAIL |
Jim Page
|
|
|
No fire alarm inspection or testings has been completed for area of work, an inspection for FIR18-00740 needs to be scheduled and passed before life fire safety inspection can be completed.
Kevin Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/15/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
BLD-Footing | 9/20/2018 | 9/21/2018 | 9/21/2018 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### 2 of three ok pending si for all ft/ compaction
|
BLD-Framing/Rough-in | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Dave Hannah
|
|
|
Kevin Phone #: ###-#### cooler walls and office walls in kitchen ok
|
BLD-Framing/Rough-in | 9/12/2018 | 9/12/2018 | 9/12/2018 | P | DEFR |
Jim Storey
|
|
|
entry by mistake on computer made ok for thursday.
|
BLD-Framing/Rough-in | 9/12/2018 | 9/13/2018 | 9/12/2018 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 7/9/2018 | 7/9/2018 | 7/9/2018 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Honeycutt n and south calf walls ok
|