BLD-Final | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | PASS |
Tony Young
|
|
|
KURT Phone #: ###-####
|
BLD-Final | 5/14/2019 | 5/15/2019 | 5/15/2019 | P | NR |
Tony Young
|
|
|
Kurt Phone #: ###-####,, needs egress width in hall way and threshholds on gym doors
|
FIRE-Final Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags, hood suppression system inspection complete, knox box is located by fire sprinkler riser room. Final life fire safety inspection complete.
Kurt Phone #: ###-####
|
FIRE-Final Inspection | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | CANC |
Jim Page
|
|
|
GC noticed that the FIR permit for sprinklers was still in issued status, GC will coordinate with the sprinkler contractor to get both inspections completed, this request is cancelled per conversation with point of contact.
Kirt Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/27/2019 | 3/27/2019 | 3/28/2019 | P | PASS |
Tony Young
|
|
|
Kurt Phone #: ###-####
|
FIRE-Final Inspection | 3/20/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Jim Page
|
|
|
Final life fire safety inspection for phase 1 TCO complete.
Curt Phone #: ###-####
|
BLD-Final | 3/20/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Tony Young
|
|
|
temporary c of O // Curt Phone #: ###-####,, temp occupancy ok
|
BLD-Ceiling Grid Inspection | 3/14/2019 | 3/14/2019 | 3/14/2019 | P | PASS |
Tony Young
|
|
|
Kurt Phone #: ###-####,, kitchen, entry and cafeteria cloud ok
|
BLD-Ceiling Grid Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 | P | PART |
Tony Young
|
|
|
Curt Phone #: ###-####,, ok after trades pass
|
BLD-Wall cover | 2/14/2019 | 2/14/2019 | 2/14/2019 | P | PART |
Tony Young
|
|
|
Curt Phone #: ###-####,, steel stud wall and soffit in lunch room ok
|
BLD-Framing/Rough-in | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PART |
Tony Young
|
|
|
Curt Phone #: ###-####,, areas ok pending trades,, mez walls ok,, locker rooms fat grid,, entry walls,, pending special inspection on welds, trusses, masonary walls, etc.
|
BLD-Aging Inspection | 12/6/2018 | 12/6/2018 | 12/8/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/5/2018 | 12/5/2018 | 12/7/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Foundation | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PART |
Tony Young
|
|
|
rebar- pouring 10:30am- Kurt Phone #: ###-####,, pending special inspection report,, also masonary walls
|
BLD-Foundation | 7/20/2018 | 7/23/2018 | 7/23/2018 | A | PART |
Tony Young
|
|
|
Curt Phone #: ###-####,, work in progress,, special inspection will happen
|
BLD-Foundation | 7/11/2018 | 7/13/2018 | 7/13/2018 | A | PART |
Jim Sly
|
|
|
rebar // Curt Phone #: ###-#### No access......OK pending special inspection, tests and approvals.
|
BLD-Foundation | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PART |
Tony Young
|
|
|
Kurt Phone #: ###-####,, grid 6 spread footings,, work in progress,, pending special inspection
|
BLD-Foundation | 7/9/2018 | 7/9/2018 | 7/9/2018 | P | PART |
Tony Young
|
|
|
rebar- Kurt Phone #: ###-####,, pending special inspection
|
BLD-Other | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PART |
Tony Young
|
|
|
foundation rebar (concrete at noon) // Curt Phone #: ###-####,, walls on line 1 and G,, pending SI report
|
BLD-Footing | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PART |
Brandon Shaw
|
|
|
Grid line G
|
BLD-Footing | 6/19/2018 | 6/19/2018 | 6/20/2018 | P | PASS |
Dave Hannah
|
|
|
Curt Phone #: ###-####
|