BLD-Final | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 10/28/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Mike Jordan
|
|
|
Reviewed email from tamarack grove engineering evaluating and accepting the cable guards.
|
BLD-Final | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PEND |
Tony Young
|
|
|
Larry Phone #: ###-####,, call for access// all ok except needs a letter from the engineer on the cable guard rails
|
BLD-Blower Door Test Results | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | DONE |
Tony Young
|
|
|
Larry Phone #: ###-####/// 3.49
|
BLD-Final | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | DEFR |
Tony Young
|
|
|
Larry Phone #: ###-####,, out of time
|
BLD-Aging Inspection | 7/10/2019 | 7/10/2019 | 7/16/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 7/9/2019 | 7/9/2019 | 7/16/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Other | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | PASS |
Tony Young
|
|
|
soffit Dry wall- Larry Phone #: ###-####,, work in progress,, ok with 2 layers
|
BLD-Other | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PART |
Tony Young
|
|
|
Dry wall- Larry Phone #: ###-####,, soffit 2 layers of 5/8" ok,, work in progress
|
BLD-Framing/Rough-in | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Energy code compliance | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Framing/Rough-in | 2/19/2019 | 2/20/2019 | 2/20/2019 | A | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, ok to insulate,, need a couple straps,, see paint
|
BLD-Wall Bracing | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | PASS |
Dave Hannah
|
|
|
Larry Phone #: ###-####
|
BLD-Foundation | 11/5/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Tony Young
|
|
|
Requesting a late am early pm inspection Phone #: ###-#### Inspection requested via web by Ben Sears
|
BLD-Foundation | 11/2/2018 | 11/2/2018 | 11/5/2018 | P | PART |
Tony Young
|
|
|
Requesting a late am early pm inspection Phone #: ###-#### Inspection requested via web by Ben Sears
|
BLD-Foundation | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | NR |
Tony Young
|
|
|
Requesting a late am early pm inspection Phone #: ###-#### Inspection requested via web by Ben Sears
|
BLD-Footing | 10/29/2018 | 10/29/2018 | 10/29/2018 | A | PASS |
Tony Young
|
|
|
Request a late morning inspection Phone #: ###-#### Inspection requested via web by Ben Sears,,
|
BLD-Foundation | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PASS |
Mike Jordan
|
|
|
Request early inspection. Concrete is will called for 10 am. We can adjust to suit your schedule Phone #: ###-#### Inspection requested via web by Ben Sears. Lower level footings only, excluding exterior columns.
|