BLD-Final | 11/12/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Jim Sly
|
|
|
Final inspection for C of O. thank you. Please call with any questions or comments. thanks, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
DOC - Permit Finaled | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 8/14/2018 | 8/16/2018 | 8/16/2018 | P | PASS |
Tony Young
|
|
|
Energy compliance. Insulation and framing corrections completed. Plans near the electrical panel. thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Energy code compliance | 8/13/2018 | 8/16/2018 | 8/14/2018 | P | CANC |
Tony Young
|
|
|
Framing corrections and insulation complete. Thanks, steve Phone #: ###-#### >> Inspection requested via web by steve hanson Inspection cancelled from web by: steve hanson
|
BLD-Framing/Rough-in | 8/8/2018 | 8/13/2018 | 8/13/2018 | A | FAIL |
Mike Jordan
|
|
|
FRaming rough in inspection. Approved plan near electrical panel. thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson. Complete lateral bracing on A01, A02 and B01 trusses. Complete interior shear walls. Hangar or pressure block rim board above main door. Correction notice posted. Ok to insulate.
|
BLD-Framing/Rough-in | 8/8/2018 | 8/10/2018 | 8/8/2018 | A | CANC |
Tony Young
|
|
|
Framing Rough inspection. Plan is near electrical panel. Thank you, steve Phone #: ###-#### >> Inspection requested via web by steve hanson Inspection cancelled from web by: steve hanson
|
BLD-Wall Bracing | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Tony Young
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 7/1/2018 | 7/2/2018 | 7/2/2018 | A | PASS |
Tony Young
|
|
|
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|