BLD-Final | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Dave Hannah
|
|
|
Bob Phone #: ###-####
|
DOC - Permit Finaled | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | NH |
Mike Jordan
|
|
|
Bob Phone #: ###-####. No access, doors locked. Called bob prior to arriving, left message. no call back. will need to reschedule.
|
BLD-Final | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | NR |
Jim Sly
|
|
|
Bob Phone #: ###-#### Need Plumbing final. Left V/M for contractor.
|
BLD-Energy code compliance | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PASS |
Brandon Shaw
|
|
|
Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2018 | 8/6/2018 | 8/6/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PASS |
Tony Young
|
|
|
Shear // Bob Phone #: ###-####
|
BLD-Conference | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PART |
Tony Young
|
|
|
Bob Phone #: ###-####,, side porch caved in,, ok to pour new footing meeting set back
|
BLD-Foundation | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PART |
Tony Young
|
|
|
Bob Phone #: ###-####,, footing ok,, need to meet setback
|