BLD-Aging Inspection | 7/16/2020 | 7/16/2020 | 7/20/2020 | | CANC |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 7/15/2020 | 7/15/2020 | 7/17/2020 | | PEND |
Tell Riley
|
|
|
no request for inspection
|
BLD-Framing/Rough-in | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Dave Hannah
|
|
|
Shane Phone #: ###-####
|
BLD-Energy code compliance | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Tell Riley
|
|
|
call for access- Shane Phone #: ###-####//ok to insulate//truss docs sent via email-no bracing required//call for insulation inspection//
|
BLD-Framing/Rough-in | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | NR |
Tell Riley
|
|
|
Shane Phone #: ###-####//needs mechanical rough in inspection//need to complete air seal//have plans and truss documents onsite//add support legs to overbuild//
|
BLD - Request for Extension | 11/1/2019 | 11/4/2019 | 11/4/2019 | A | DEFR |
Brandon Shaw
|
|
|
Shane Phone #: ###-####
|
Extend Permit 90/180 days | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | DONE |
Brandon Shaw
|
|
|
Shane Phone #: ###-####
|
BLD-Framing/Rough-in | 5/3/2019 | 5/7/2019 | 5/7/2019 | P | NR |
Jim Sly
|
|
|
for addition siding is done, roof is done // Shane Phone #: ###-#### Need all trade Approvals
|
BLD-Conference | 5/3/2019 | 5/3/2019 | 5/5/2019 | P | CANC |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | NR |
Mike Jordan
|
|
|
Call half hour to meet // Shane Phone #: ###-####. Needs to rough in MEP's and get get inspected first.
|
BLD-Foundation | 8/8/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Brandon Shaw
|
|
|
Rick Phone #: ###-####
|
BLD-Footing | 8/7/2018 | 8/8/2018 | 8/8/2018 | P | PASS |
Jim Sly
|
|
|
Rick Phone #: ###-####
|