BLD-Final | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | DONE |
Mike Jordan
|
|
|
Pls contact Brad (Foreman) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
|
DOC - Permit Finaled | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 8/24/2018 | 8/27/2018 | 8/27/2018 | P | CANC |
Mike Jordan
|
|
|
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
|
BLD-Footing | 8/27/2018 | 8/27/2018 | 8/27/2018 | P | PART |
Mike Jordan
|
|
|
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes. Did not have the city approved set of plans. Ok to proceed at contractors own risk.
|