BLD-Final | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.65
|
BLD-Framing/Rough-in | 11/29/2018 | 11/30/2018 | 11/30/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to cover...
|
BLD-Framing/Rough-in | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Energy code compliance | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Other | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 11/26/2018 | 11/26/2018 | 11/26/2018 | P | FAIL |
Brandon Shaw
|
|
|
Anchor bolts to be with in 12" of sill plate ends, 4 locations... Shear edge nailing missed, 2nd floor SW corner... A7 2 ply truss- fastener schedule, bottom cord, 3 rows, 2" O.C... See Red Paint OK to insulate
|
BLD-Wall Bracing | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Interior OSB shear and missing anchor bolts to be installed before framing rough-in...
|
BLD-Wall Bracing | 11/6/2018 | 11/6/2018 | 11/6/2018 | P | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 10/15/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|