BLD-Final | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tony Young
|
|
|
CLOBY Phone #: ###-####
|
DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | NH |
Tony Young
|
|
|
CLOBY Phone #: ###-####,, locked,, no text back
|
BLD-Energy code compliance | 5/14/2019 | 5/15/2019 | 5/16/2019 | P | PASS |
Tony Young
|
|
|
Colby Phone #: ###-####
|
BLD-Framing/Rough-in | 5/10/2019 | 5/13/2019 | 5/14/2019 | P | PASS |
Tony Young
|
|
|
Cory Phone #: ###-####
|
BLD-Wall Bracing | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-####
|
BLD-Other | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | DONE |
Jim Sly
|
|
|
second layer sheet rock // Colby Phone #: ###-#### 1st floor
|
BLD-Wall Bracing | 4/3/2019 | 4/3/2019 | 4/3/2019 | P | PART |
Jim Sly
|
|
|
Colby-dry wall Phone #: ###-#### Rated wall 1st layer OK.
|
BLD-Footing | 3/21/2019 | 3/21/2019 | 3/22/2019 | P | PART |
Tony Young
|
|
|
Colby Phone #: ###-####,, interior slab footings, work in progress, ok
|
BLD-Foundation | 3/7/2019 | 3/8/2019 | 3/8/2019 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 3/6/2019 | 3/7/2019 | 3/7/2019 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress
|