BLD-Final | 5/13/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Dave Hannah
|
|
|
The HVAC inspection happened today after the pressure balance test was completed. Their inspector said he would have it signed off tomorrow morning. Thanks Phone #: ###-#### Inspection requested via web by Dustin Collins
|
DOC - Permit Finaled | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 1/29/2019 | 1/31/2019 | 1/31/2019 | A | PART |
Dave Hannah
|
|
|
Insulation will be completed on Wednesday. We will be ready for installation prior to cover Thursday morning. Thank you Phone #: ###-#### Inspection requested via web by Dustin Collins ok to cover all but for ceiling in front room
|
BLD-Framing/Rough-in | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Dustin Collins
|
BLD-Conference | 1/2/2019 | 1/2/2019 | 1/9/2019 | P | DONE |
Dave Hannah
|
|
|
concern about building materials not being cleaned up.
|
BLD-Wall Bracing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Hold downs and floor to floor straps to be installed before framing rough-in...
|
BLD-Other | 11/28/2018 | 11/28/2018 | 11/29/2018 | P | DONE |
Dave Hannah
|
|
|
Neighbors are concerned about the building materials/trash on the sidewalk/street.
|
BLD-Foundation | 11/9/2018 | 11/9/2018 | 11/10/2018 | P | PASS |
Dave Hannah
|
|
|
steam wall ... as late as possible // Kevin Phone #: ###-####
|
BLD-Foundation | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | NR |
Dave Hannah
|
|
|
stem wall // Kevin Phone #: ###-####
|
BLD-Footing | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Dave Hannah
|
|
|
Kevin Phone #: ###-####
|