BLD-Final | 6/4/2019 | 6/5/2019 | 6/5/2019 | P | PASS |
Jim Storey
|
|
|
We request a PM Building Final Inspection for the In Ground Spa at Reedhouse Clubhouse
Point of contact Miles Gastil ###-#### Phone #: ###-#### Inspection requested via web by James Thomas per the reviewed plan.
|
FIRE-Final Inspection | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher was placed at time of inspection with current inspection tags. Final life fire safety inspection per city approved drawings complete.
We request a late AM Life Safety Inspection for the In Ground Spa at Reedhouse Clubhouse
Point of contact Miles Gastil ###-#### Phone #: ###-#### Inspection requested via web by James Thomas
|
BLD-Conference | 5/29/2019 | 5/30/2019 | 5/31/2019 | A | NR |
Jim Storey
|
|
|
Miles Phone #: ###-#### pending BO JBlais review of plans to meet IBC.
|
BLD-Conference | 5/23/2019 | 5/24/2019 | 5/31/2019 | A | NR |
Jim Storey
|
|
|
Miles Phone #: ###-#### pending BO JBlais review of plans to meet IBC.
|
BLD-Framing/Rough-in | 5/17/2019 | 5/20/2019 | 5/20/2019 | A | PASS |
Jim Storey
|
|
|
Miles Phone #: ###-#### non combustable framing on for cover pending others
|
BLD-Framing/Rough-in | 5/16/2019 | 5/17/2019 | 5/17/2019 | P | CANC |
Jim Storey
|
|
|
CANCEL INP DUE TO WETHER-We request a framing for cover inspection on the Outdoor Kitchen (Metal Stud Framing).
Regards, Miles Gastil Phone #: ###-#### >> Inspection requested via web by James Thomas
|
BLD-Wall cover | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Jim Storey
|
|
|
We are requesting an inspection for the Outdoor Kitchen pony wall and sheer wall framing for cover.
Regards,
James T. Thomas ###-#### Phone #: ###-#### Inspection requested via web by James Thomas
|
BLD-Footing | 3/28/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Brandon Shaw
|
|
|
We would like an afternoon inspection on the rebar ; WWF for the Outdoor Kitchen slab, turn down sidewalk and column footings.
James T. Thomas ###-#### Phone #: ###-#### Inspection requested via web by James Thomas
|
BLD-Energy code compliance | 3/28/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Brandon Shaw
|
|
|
We would like a PM inspection for the closed cell foam insulation installation at the Indoor Kitchen Expansion: floor joists, walls, ceiling, etc. The drywall team would like to hang on Saturday morning in this area.
Regards,
James T. Thomas ###-#### Phone #: ###-#### Inspection requested via web by James Thomas
|
BLD-Wall cover | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Brandon Shaw
|
|
|
Framing rough-in...
|
BLD-Concrete | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PART |
Jim Storey
|
|
|
REBAR // Marc Phone #: ###-#### placing w/si
|
BLD-Foundation | 3/15/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Jim Storey
|
|
|
Marc-rebar Phone #: ###-####
|
BLD-Framing/Rough-in | 3/13/2019 | 3/15/2019 | 3/15/2019 | P | PASS |
Jim Storey
|
|
|
Marc Phone #: ###-####
|
BLD-Foundation | 3/13/2019 | 3/15/2019 | 3/15/2019 | A | PART |
Jim Storey
|
|
|
rebar, 10 concrete // Marc Phone #: ###-#### placed with si pending report
|
BLD-Foundation | 3/12/2019 | 3/13/2019 | 3/13/2019 | A | CANC |
Jim Storey
|
|
|
rebar // Mark Phone #: ###-####
|
BLD-Foundation | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PASS |
Jim Storey
|
|
|
Marc- Rebar inspection Phone #: ###-####
|
BLD-Foundation | 3/5/2019 | 3/6/2019 | 3/6/2019 | A | PASS |
Jim Storey
|
|
|
rebar ready around 10 // Marc Phone #: ###-#### pending si rebar ok
|