BLD-Conference | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PART |
Mike Jordan
|
|
|
Earliest available consultation meeting, Permit Card Phone #: ###-#### Inspection requested via web by Kris Linnell. Ok for temp occ.
|
BLD-Final | 7/5/2020 | 7/6/2020 | 7/6/2020 | A | PEND |
Mike Jordan
|
|
|
Building final for TCO Phone #: ###-#### Inspection requested via web by Kris Linnell. Will be ok for temp occ. once zoning signs off on bond and issues temp.
|
BLD-Final | 7/1/2020 | 7/2/2020 | 7/2/2020 | P | NR |
Mike Jordan
|
|
|
Building Final inspection Phone #: ###-#### Inspection requested via web by Kris Linnell
|
FIRE-Final Inspection | 7/1/2020 | 7/2/2020 | 7/2/2020 | P | PART |
Greg Ruxton
|
|
|
Fire life safety inspection of building completed and code compliant. Contractor to finish hanging undercounter FE's on brackets prior to building final inspection. Area of concern is aerial fire apparatus access. Travel distance exceeds 150 ft and required approved turnaround code not be verified.
Fire Life ; Safety for Temp Occupancy to allow Tenant Touring of interiors of apartments. Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Ceiling Grid Inspection | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | CANC |
Jim Storey
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Mike Jordan
|
|
|
Building 12 East 12 unit drop ceiling locations framing and fire caulking. Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Framing/Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PART |
Mike Jordan
|
|
|
Drop Ceiling Framing inspections in 05 and 06 units in first, second, and third floors. Phone #: ###-#### Inspection requested via web by Kris Linnell. Fir downs ok to cover pending mech at fire damper areas.
|
BLD-Energy code compliance | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Mike Jordan
|
|
|
Building 12 - 1st Floor, Insulation, Vapor Barrier ; RC Channel inspection. Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Mike Jordan
|
|
|
Building 12 - 1st Floor Energy Seal, Fire Caulking ; Framing Building 12 - 2nd Floor Ceilings 1st layer gyp and 2nd layer gyp overlap Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
BLD-Wall cover | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | CANC |
Mike Jordan
|
|
|
Building 12 - 2nd Floor Insulation and RC channel inspection for cover. Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
BLD-Energy code compliance | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Mike Jordan
|
|
|
Building 12 - 2nd Floor Insulation and RC channel inspection for cover. Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
BLD-Framing/Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Mike Jordan
|
|
|
Re-inspection of Fire Stopping, Energy Code and Framing for Building 12 - 2nd Floor Units cover for Insulation ; Vapor Barrier install. As late as possible this afternoon.
6" OSA intakes at west units (105, 106, 205, 206, 305 ; 306) being addressed by Mech Eng, front of furnace alcoves not being covered until after ceiling drops framing inspection. Phone #: ###-#### Inspection requested via web by Bob Goodwin. Ok to insulate 2nd. floor only.
|
BLD-Framing/Rough-in | 1/16/2020 | 1/16/2020 | 1/17/2020 | P | PART |
Mike Jordan
|
|
|
2nd. floor, neeeds to complee firecaulking at toilets and tub drains. Provide UL listed assembly for through penetrations of fresh air intakes at 1hr. fire barrier walls.
|
BLD-Energy code compliance | 1/15/2020 | 1/15/2020 | 1/15/2020 | P | PASS |
Mike Jordan
|
|
|
Third Floor Insulation vapor barreir and RC Channel on Ceiling and walls. Phone #: ###-#### Inspection requested via web by Kris Linnell. 3rd floor only ok to rock.
|
BLD-Framing/Rough-in | 1/14/2020 | 1/14/2020 | 1/14/2020 | P | PASS |
Mike Jordan
|
|
|
Late A.M. Early P.M. to allow for Mechanical inspection on exhaust fan GWB Fire boxes. Framing Corrections and Mechanical failures from last walk have been corrected. Framing and Energy seal inspection for cover on third floor only. Phone #: ###-#### Inspection requested via web by Kris Linnell. 3rd. floor only ok to insulate.
|
BLD-Framing/Rough-in | 1/13/2020 | 1/14/2020 | 1/14/2020 | A | NR |
Mike Jordan
|
|
|
Late A.M. Early P.M. to allow for Mechanical inspection on exhaust fan GWB Fire boxes. Framing Corrections and Mechanical failures from last walk have been corrected. Framing and Energy seal inspection for cover on third floor only. Phone #: ###-#### Inspection requested via web by Kris Linnell. Moved to pm inspection.
|
BLD-Framing/Rough-in | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | FAIL |
Mike Jordan
|
|
|
Energy Seal, Fire caulking and Framing for Cover Third Floor. Preferably as early as possible. Phone #: ###-#### Inspection requested via web by Kris Linnell. Needs to resolve vent fan install, install missing H2.5, LPT4 and missed fire caulking.
|
BLD-Energy code compliance | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PART |
Tony Young
|
|
|
Energy Code inspection of pre-insulation areas for pre-rock installations in Buidling 12. Phone #: ###-#### Inspection requested via web by Bob Goodwin,, ok to cover insulated areas for pre-rock
|
BLD-Framing/Rough-in | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PART |
Mike Jordan
|
|
|
Framing inspection in pre-rock areas. Phone #: ###-#### Inspection requested via web by Kris Linnell. Pre rock and fire caulking. work in progress.
|
BLD-Framing/Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | CANC |
Mike Jordan
|
|
|
Earliest availability preferred. Inspect remaining Sheathing nailing on SE Corner of Building 12. Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Wall Bracing | 11/19/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Mike Jordan
|
|
|
Earliest availability preferred. Inspect remaining Sheathing nailing on SE Corner of Building 12. Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Framing/Rough-in | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | CANC |
Mike Jordan
|
|
|
Exterior Nail inspection Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Wall Bracing | 11/12/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Mike Jordan
|
|
|
Exterior Nail inspection Phone #: ###-#### Inspection requested via web by Kris Linnell. Exterior and interior shear walls, floors 1 to 3 ok to cover.
|
BLD-Framing/Rough-in | 10/18/2019 | 10/21/2019 | 10/21/2019 | P | FAIL |
Mike Jordan
|
|
|
First Floor Shear Inspection Phone #: ###-#### Inspection requested via web by Kris Linnell. 1st floor shear, missing fateners and holddowns.
|
BLD-Conference | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | DONE |
Mike Jordan
|
|
|
Per Mike Jordan, Framing Consultation prior to framing for building 12. Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Concrete | 9/10/2019 | 9/11/2019 | 9/11/2019 | P | PART |
Tell Riley
|
|
|
Building Slab and interior footing pour scheduled for 6A.M. Thursday Morning. Phone #: ###-#### Inspection requested via web by Kris Linnell//vapor barrier ok//add bar to footings as discussed onsite// ok pending specials//
|
BLD-Foundation | 8/23/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Mike Jordan
|
|
|
Building 11 North Half Stem Walls Rebar inspection. Concrete pour set for Tuesday 0730. Phone #: ###-#### Inspection requested via web by Kris Linnell
|
BLD-Energy code compliance | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | PASS |
Mike Jordan
|
|
|
chris Phone #: ###-####. Rifid insulation on interior of stemwall under slab on grade.
|
BLD-Foundation | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PART |
Tell Riley
|
|
|
Bob-stem wall-says plan mod is for sewer not for this inspection Phone #: ###-####//north end building//walls ok pending specials// adjust wall rebar at location discussed onsite//
|
BLD-Footing | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PART |
Mike Jordan
|
|
|
Concrete at 1230 // bob Phone #: ###-####. Perimeter footings and column pad footings. Will have special inspection. Noted several areas were rebar does not have the 3 inch minimum clearance required. Special inspector to verify 3inch min. clearance prior to concrete placement.
|