BLD-Final | 6/4/2019 | 6/4/2019 | 6/4/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Allen
|
DOC - Permit Finaled | 6/4/2019 | 6/4/2019 | 6/4/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/17/2019 | 5/17/2019 | 5/17/2019 | P | NR |
Dave Hannah
|
|
|
HVAC final is scheduled for am. Please call me prior to heading that way. I will meet you ang get you access to the property. Thanks. -Ryan Allen Phone #: ###-#### Inspection requested via web by Ryan Allen
|
BLD-Energy code compliance | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PASS |
Brandon Shaw
|
|
|
This is the pool house...
|
BLD-Framing/Rough-in | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Foundation | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Dave Hannah
|
|
|
If at all possible, could we request a later morning inspection. Forms and dowels will be set tomorrow first thing in morning. Mud is going to deliver at 2pm. Please contact Aaron, concrete contractor, his number is the one listed in request. Thanks Phone #: ###-#### Inspection requested via web by Ryan Allen
|
BLD-Conference | 1/8/2019 | 1/9/2019 | 1/9/2019 | A | PASS |
Dave Hannah
|
|
|
My concrete contractor would like a confrence reguarding some complications due to an existing concrete structure in the area he is putting a footing and foundation wall. Access to the area we are working on is on Coston St on north east corner of wood fenced area of property. Near dump trailer. Thanks Phone #: ###-#### Inspection requested via web by Ryan Allen
|