BLD-Final | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Tell Riley
|
|
|
Appears that all associated trade permits have been finaled. Final project/permit if no outstanding building issues. Bob A.//complete per plan mod//window trim to be sealed with waterproof sealer per owner//
|
DOC - Permit Finaled | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Tell Riley
|
|
|
Complete per plan modification//window trims are to be sealed with waterproof sealer per owner//
|
BLD-Conference | 11/5/2019 | 11/5/2019 | 11/5/2019 | P | DONE |
Tell Riley
|
|
|
Assist with other trades.//Cn given to owner//will need to submit plan mod for showers in sunroom//also let her know that if dwelling is to be used as a business that a new application will need to be submitted for a business//
|
BLD-Final | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | NR |
Tell Riley
|
|
|
Charity-call prior to meet for access Phone #: ###-####//need plumbing final//all other areas ok//
|
BLD-Aging Inspection | 8/21/2019 | 8/21/2019 | 8/21/2019 | | PASS |
Tell Riley
|
|
|
Expires: 10/05/19
|
BLD-Aging Inspection | 8/20/2019 | 8/20/2019 | 8/21/2019 | | DONE |
Tell Riley
|
|
|
|
BLD-Energy code compliance | 4/8/2019 | 4/8/2019 | 4/8/2019 | P | PASS |
Jim Storey
|
|
|
John will be the contact. This inspection is for insulation in the addition. Thank you and have a great day. Phone #: ###-#### Inspection requested via web by Laura Longshaw
|
BLD-Framing/Rough-in | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Jim Sly
|
|
|
Darius.....208 514 5493
|
BLD-Framing/Rough-in | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | CANC |
Jim Sly
|
|
|
Framing Rough in for addition Darius is the contact. Phone #: ###-#### Inspection requested via web by Laura Longshaw
|
BLD-Framing/Rough-in | 3/22/2019 | 3/25/2019 | 3/25/2019 | P | NR |
Jim Sly
|
|
|
Rough in inspection for addition please. Contact will be Fred Yetter. Thank you and have a great day! Phone #: ###-#### Inspection requested via web by Laura Longshaw Need approved plans.
|
BLD-Framing/Rough-in | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | NR |
Jim Sly
|
|
|
Framing inspection. Please call Darius at ###-#### with any questions. We will be onsite. Thank you and have a good day! Phone #: ###-#### Inspection requested via web by Laura Longshaw C/N need Mech and Plumb R / I approval. Need air seal Pkg.
|
BLD-Foundation | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Jim Sly
|
|
|
Brian Phone #: ###-#### The plans will be by the sliding door on the floor. Please call brian if any questions. Mono pour footing and wall.
|
BLD-Framing/Rough-in | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PART |
Jim Sly
|
|
|
Inspection is for the beams installed in the ceiling only. Please call Darius when you are on your way ###-#### or if you have any questions. The door code is 3050. After you click on the unlock button you will need to pull the door slightly to release the pressure on the door. There is no one living at the property and there are no animals. Thank you so much and have a super day! Phone #: ###-#### Inspection requested via web by Laura Longshaw Beams above the ceiling line.......OK.
|