BLD-Framing/Rough-in | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2019 | 3/25/2019 | 3/25/2019 | P | FAIL |
Mike Jordan
|
|
|
Ed Phone #: ###-####. Repairs done incorrectly. Went over plans with contractor on how to install the blocking and A35's.
|
BLD-Framing/Rough-in | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | FAIL |
Mike Jordan
|
|
|
Ed Phone #: ###-####. Needs to install blocking at every other truss and connect with 2 A35's per the approved drawings and engineering.
|
BLD-Foundation | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####
|
BLD-Footing | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. Issues resolved.
|
BLD-Footing | 2/27/2019 | 2/28/2019 | 2/28/2019 | A | FAIL |
Mike Jordan
|
|
|
Ned Phone #: ###-####. Footings full of water, need longer lap length fromm existing to new, 36 inches per the engineering.
|
BLD-Footing | 2/19/2019 | 2/20/2019 | 2/19/2019 | P | DONE |
Mike Jordan
|
|
|
Ed Phone #: ###-####
|