BLD-Final | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | PASS |
Jim Storey
|
|
|
Please call and I can meet you on site. Phone #: ###-#### Inspection requested via web by Chad Queen
|
DOC - Permit Finaled | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 | | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Jim Storey
|
|
|
Drywall will be loaded in the building tomorrow afternoon. Thank you Phone #: ###-#### Inspection requested via web by Chad Queen
|
BLD-Framing/Rough-in | 10/2/2019 | 10/2/2019 | 10/2/2019 | A | PASS |
Jim Storey
|
|
|
c/n made ok/ foam insulation roof ok/
|
BLD-Framing/Rough-in | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PASS |
Jim Storey
|
|
|
Chad Phone #: ###-#### under floor ok to cover pending trade insp.
|
BLD-Framing/Rough-in | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | PART |
Jim Storey
|
|
|
Documents and Manual J on site by stair case Phone #: ###-#### Inspection requested via web by Chad Queen fire blk cielling at chase box/airseal all vertcal penatrations ie wire , pipes ect./finsh duct ceilling fur down.
|
BLD-Wall Bracing | 7/10/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-####
|
BLD-Foundation | 6/21/2019 | 6/21/2019 | 6/21/2019 | P | PEND |
Jim Storey
|
|
|
Chad Phone #: ###-#### p/l
|
BLD-Concrete | 6/21/2019 | 6/21/2019 | 6/21/2019 | P | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-#### r value ok under slab
|
BLD-Foundation | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | FAIL |
Jim Storey
|
|
|
Chad-foundation wall Phone #: ###-####// ......No property pins located. No string lines pulled. Unable to determine if setbacks were met. If Contractor proceeds to pour foundation.......they are continuing at own risk.// min r-10 under slab non value on product do not place until reinspect bfor prop. line and r value are verified.
|
BLD-Foundation | 5/21/2019 | 5/22/2019 | 5/22/2019 | P | PART |
Jim Sly
|
|
|
Chad Phone #: ###-#### See previous Footing inspection notes.......
|
BLD-Footing | 5/16/2019 | 5/20/2019 | 5/20/2019 | P | PART |
Jim Sly
|
|
|
Chad Phone #: ###-#### Called contractor......No property pins located. No string lines pulled. Unable to determine if setbacks were met. If Contractor proceeds to pour foundation.......they are continuing at own risk.
|