FIRE-Final Inspection | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | FAIL |
Jim Page
|
|
|
Fire alarm panel has open circuit trouble on NAC circuit, panel needs to be normal for life fire safety inspection. A fire alarm vendor will need to be present for the life fire safety inspection, due to fire alarm devices being removed and re-installed during this scope of work a fire alarm test will be required to verify proper operation of fire alarm system in scope of work areas.
Tom Phone #: ###-####
|
BLD-Final | 11/7/2019 | 11/8/2019 | 11/14/2019 | P | PEND |
Dave Hannah
|
|
|
Tom Phone #: ###-#### needs fire first
|
FIRE-Final Inspection | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | FAIL |
Jim Page
|
|
|
Architectural feature at bottom of escalator is not installed, fire sprinkler head is to far down from deck, feature needs to be in place for final sign off. Need a fire alarm vendor available to test fire alarm system as discussed as verbally discussed, audio visual devices were removed and re-installed during project, need to verify operation.
Tom Phone #: ###-####
|
BLD-Conference | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | DONE |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
FIRE-Conference | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | DONE |
Troy Cobbley
|
|
|
** Met with Tom. Discussed exit lighting, fire sprinkler, and fire alarm placement questions he had. He is going to meet with the architect to go over items we discussed.**MAS***Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2019 | 9/4/2019 | 9/5/2019 | P | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
BLD-Foundation | 7/17/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Dave Hannah
|
|
|
TOM- REBAR INSPECTION Phone #: ###-####
|